Fox Covert Solar Farm (22 MW)

Fox Covert Solar Farm is a 22 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 October 2023; the record was last updated on 12 October 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
operationalstatus in REPD
12 October 2023record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
3 August 2020Application submitted
1 June 2021Planning permission granted
12 October 2023Operational

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
operational
Record last updated
12 October 2023
Operator or applicant
Low Carbon
Planning authority
Buckinghamshire
Planning application reference
20/02582/APP
Site area
47.0 ha
Address (REPD)
Fox Covert Solar Farm, Great Horwood, Milton Keynes
Council area (by location)
Buckinghamshire
Time to decision
43 weeks
Contracts for Difference
AR4
REPD reference
7958

The scheme also includes battery storage, recorded separately in REPD (operational).

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tuckey Farmsolar farm25approved, not built3.3
East Claydon Substation, East Claydon Roadbattery storage500application submitted3.8
Wood End, Mursley Roadsolar farm36approved, not built3.9
Thornton Estatesolar farm50application submitted4.5
East Claydon Battery Energy Storagebattery storage500approved, not built4.7
Hogshaw Road, Granboroughbattery storage99application withdrawn4.9
Land at Thornborough Groundssolar farm5operational5.3
Manor Farmsolar farm12approved, not built5.4
Longbreach Solar Farmsolar farm49.9application submitted5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9626, -0.9007).