Longbreach Solar Farm (49.9 MW)

Longbreach Solar Farm is a 49.9 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 17 June 2025, no decision recorded; the record was last updated on 8 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedstatus in REPD
8 August 2025record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
17 June 2025Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
8 August 2025
Operator or applicant
Noventum Power Limited
Planning authority
Buckinghamshire
Planning application reference
25/01865/APP
Site area
64.1 ha
Address (REPD)
Wings Farm Marston Road Granborough
Council area (by location)
Buckinghamshire
REPD reference
14279

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hogshaw Road, Granboroughbattery storage99application withdrawn0.8
East Claydon Battery Energy Storagebattery storage500approved, not built1.3
Tuckey Farmsolar farm25approved, not built2.8
East Claydon Substation, East Claydon Roadbattery storage500application submitted3.2
Fox Covert Solar Farmsolar farm22operational5.7
Wood End, Mursley Roadsolar farm36approved, not built6.8
Knapps Hook Farmsolar farm8.9application withdrawn7.2
Littleton Green Energy Parksolar farm10application submitted7.3
Littleton Green Energy Parkwind turbine6.2application submitted7.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9122, -0.887).