Energy Projects Near You

Bumpers Farm Phase 2 (12 MW solar farm)

Bumpers Farm Phase 2 is a 12 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 October 2015, not yet built; the record was last updated on 4 June 2020. REPD also records that the planning permission expired on 26 October 2018, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
approved, not builtmay be out of datestatus in REPD
4 June 2020record last updated
Buckinghamshirecouncil area

REPD also records that the planning permission expired on 26 October 2018, so the project may not go ahead in this form.

Planning timeline

DateStage
11 July 2014Application submitted
5 September 2014Refused by the planning authority
4 February 2015Appeal lodged
26 October 2015Planning permission granted
26 October 2015Appeal allowed
26 October 2018Permission expired

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
approved, not built
Record last updated
4 June 2020
Operator or applicant
Anesco
Planning authority
Buckinghamshire
Planning application reference
14/01926/APP
Appeal reference
APP/K0425/W/14/3001711
Site area
50.0 ha
Address (REPD)
Land North Of Bumpers Farm, Ilmer Lane, Ilmer, Buckinghamshire
Council area (by location)
Buckinghamshire
Time to decision
67 weeks
REPD reference
6282

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bumpers Farm Phase 1solar farm5operational<0.1
Bumpers Lane Solar Farmbattery storage13.3operational0.6
Whirlbush Farm, Kingsey Solar Farm & Battery Storagesolar farm49.9approved, not built1.1
Callie's Solar Farmsolar farm49.9approved, not built2.0
Forty Green Farmsolar farm7.5refused2.5
Kimblewick Road Solar Farmsolar farm40approved, not built4.1
Moat Farm Solar Farmsolar farm24.1approved, not built6.8
Postcombesolar farm49.9application submitted8.4
Dodwells Solar Farmsolar farm49.9approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7483, -0.8963).