Energy Projects Near You

Dodwells Solar Farm (49.9 MW)

Dodwells Solar Farm is a 49.9 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 August 2023, not yet built; the record was last updated on 3 February 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
3 February 2023record last updated
South Oxfordshirecouncil area

Planning timeline

DateStage
23 September 2021Application submitted
23 August 2023Planning permission granted
23 August 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
3 February 2023
Operator or applicant
Opdenergy UK Limited
Planning authority
South Oxfordshire
Planning application reference
P21/S3915/FUL
Site area
112.0 ha
Address (REPD)
Dodwells Solar Farm On Land North Of The A40 Between Milton Common & Tetsworth
Council area (by location)
South Oxfordshire
Time to decision
100 weeks
REPD reference
8539

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Harlesford Solar Farmsolar farm49.9approved, not built0.8
Cornwell Solar Farmsolar farm49.9approved, not built2.2
Postcombesolar farm49.9application submitted3.0
Easington Farm (Chalgrove)solar farm21.3operational5.8
Forty Green Farmsolar farm7.5refused8.1
Bumpers Farm Phase 1solar farm5operational8.6
Bumpers Farm Phase 2solar farm12approved, not built8.6
Whirlbush Farm, Kingsey Solar Farm & Battery Storagesolar farm49.9approved, not built9.0
Bumpers Lane Solar Farmbattery storage13.3operational9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7103, -1.0057).