Energy Projects Near You

Harlesford Solar Farm (49.9 MW)

Harlesford Solar Farm is a 49.9 MW solar farm project in South Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 December 2021, not yet built; the record was last updated on 18 October 2022. REPD records the planning permission as expiring on 16 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
18 October 2022record last updated
South Oxfordshirecouncil area

REPD records the planning permission as expiring on 16 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
16 September 2020Application submitted
16 December 2021Planning permission granted
16 December 2024Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
18 October 2022
Operator or applicant
Harlesford Solar Farm Limited
Planning authority
South Oxfordshire
Planning application reference
P20/S3245/FUL
Site area
79.0 ha
Address (REPD)
Harlesford Farm, Stoke Talmage Road, Tetsworth, Thame
Council area (by location)
South Oxfordshire
Time to decision
65 weeks
Contracts for Difference
AR4
REPD reference
7956

Who decides

ApplicationsSouth OxfordshireUK
Decided applications (solar, wind, battery)3310,236
Refused9 (27%)19%
Solar refused4 of 2312%
Battery storage refused5 of 1016%
Median time from submission to decision21.4 weeks17.0 weeks
Appeals lodged / allowed1 / 4—

UK: all UK planning authorities. Counted under these REPD planning authority names: Oxfordshire, South Oxfordshire.

Other large projects within 10 km

ProjectTypeMWStatuskm
Dodwells Solar Farmsolar farm49.9approved, not built0.8
Cornwell Solar Farmsolar farm49.9approved, not built1.5
Postcombesolar farm49.9application submitted3.0
Easington Farm (Chalgrove)solar farm21.3operational5.0
Forty Green Farmsolar farm7.5refused8.8
Bumpers Farm Phase 2solar farm12approved, not built9.4
Bumpers Farm Phase 1solar farm5operational9.4
Whirlbush Farm, Kingsey Solar Farm & Battery Storagesolar farm49.9approved, not built9.8
Bumpers Lane Solar Farmbattery storage13.3operational9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7048, -1.0131).