Energy Projects Near You

Solar, wind and battery projects near Princes Risborough (HP27)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HP27 (Buckinghamshire): 1 is waiting for a planning decision, 9 approved but not yet running, 3 operational. The largest live scheme is Callie's Solar Farm (49.9 MW solar farm, approved on 24 November 2022, not yet built; REPD status may be out of date), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
1awaiting a decision
9approved, not running
3operational

Projects within 10 km of HP27

Projects of 1 MW and more (9)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Forty Green Farmsolar farmsolar farm7.5refusedupdated Nov 2014Jan 2014refused Oct 2014Nov 2014Buckinghamshire4.0
Kimblewick Road Solar Farmsolar farmsolar farm40approved, not builtupdated Jan 2026Jul 2023granted Jan 2026Jan 2026Buckinghamshire4.8
Bumpers Farm Phase 2solar farmsolar farm12approved, not built may be out of dateupdated Jun 2020Jul 2014granted Oct 2015Jun 2020Buckinghamshire5.3
Bumpers Farm Phase 1solar farmsolar farm5operationalupdated Jun 2017Jul 2014granted Oct 2015Jun 2017Buckinghamshire5.3
Bumpers Lane Solar Farmbattery storagebattery storage13.3operationalupdated Dec 2021Nov 2016—Dec 2021Buckinghamshire5.4
Callie's Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Mar 2022granted Nov 2022Apr 2022Buckinghamshire5.5
Whirlbush Farm, Kingsey Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Jul 2021granted Mar 2022Apr 2022Buckinghamshire6.2
Moat Farm Solar Farmsolar farmsolar farm24.1approved, not built may be out of dateupdated Mar 2022Aug 2021granted Feb 2022Mar 2022Buckinghamshire7.0
Thame solar farmsolar farmsolar farm4.3operationalupdated Feb 2017Jul 2014granted Oct 2015Feb 2017South Oxfordshire7.6
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Holly Green Farm, Sandpit Lanerooftop solarrooftop solar—approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Buckinghamshire3.2
Whirlbush Farm, Kingsey Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Jul 2021granted Mar 2022Apr 2022Buckinghamshire6.2
Haddenham Garden Centre, Stanbridge Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Jan 2023granted Feb 2023Mar 2023Buckinghamshire8.2
Lucy Switchgear, Howland Roadrooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Dec 2023Dec 2023South Oxfordshire8.7
Howland Road Energy Storage Facilitybattery storagebattery storage0.2application submittedupdated May 2026Mar 2026—May 2026South Oxfordshire8.8

Distance from the average position of the HP27 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm80521176
Rooftop solar303000.7
Battery storage311100.2

MW in pipeline: pending, approved and under-construction capacity.

How Buckinghamshire decides solar, wind and battery applications

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

All projects in Buckinghamshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HP27, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.