Energy Projects Near You

Solar, wind and battery projects near High Wycombe (HP14)

9 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HP14 (Buckinghamshire): 6 approved but not yet running. The largest live scheme is Eden Shopping Centre, Oxford Road, (0.6 MW rooftop solar, approved on 13 September 2023, not yet built), 6.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9projects within 10 km
0awaiting a decision
6approved, not running
0operational

Projects within 10 km of HP14

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Forty Green Farmsolar farmsolar farm7.5refusedupdated Nov 2014Jan 2014refused Oct 2014Nov 2014Buckinghamshire8.9
Land North of Marlow Landfill Sitesolar farmsolar farm5refusedupdated Mar 2015Sep 2015refused Feb 2016Mar 2015Buckinghamshire10.0
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hawes Recycling Centre, Coronation Roadrooftop solarrooftop solar0.7refusedupdated Feb 2025Nov 2024refused Feb 2025Feb 2025Buckinghamshire5.5
Eden Shopping Centre, Oxford Road,rooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Buckinghamshire6.4
Newlands Meadow, Edenrooftop solarrooftop solar0.1approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Buckinghamshire6.4
Wycombe Leisure Centre, Handy Crossrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Buckinghamshire6.8
Big Yellow Self Storage, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Buckinghamshire8.3
Holly Green Farm, Sandpit Lanerooftop solarrooftop solar—approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Buckinghamshire8.7
Holmer Green Senior Schoolrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Jul 2024granted Sep 2024Nov 2024Buckinghamshire9.8

Distance from the average position of the HP14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm200020
Rooftop solar706011.6

MW in pipeline: pending, approved and under-construction capacity.

How Buckinghamshire decides solar, wind and battery applications

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

All projects in Buckinghamshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.