Energy Projects Near You

Solar, wind and battery projects near Great Missenden (HP16)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HP16 (Buckinghamshire): 1 is waiting for a planning decision, 5 approved but not yet running. The largest live scheme is Mop End Farm, Mop End Lane (500 MW battery storage, application submitted on 15 August 2025, no decision recorded), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
5approved, not running
0operational

Projects within 10 km of HP16

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mop End Farm, Mop End Lanebattery storagebattery storage500application submittedupdated Sep 2025Aug 2025—Sep 2025Buckinghamshire5.6
Lye Green Energy Storagebattery storagebattery storage25refused on appealupdated Jun 2019Jun 2018—Jun 2019Buckinghamshire9.3
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Holmer Green Senior Schoolrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Jul 2024granted Sep 2024Nov 2024Buckinghamshire4.3
Bellingdon Brickworks, Chesham Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Oct 2025granted Jan 2026Apr 2026Buckinghamshire7.0
Eden Shopping Centre, Oxford Road,rooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Buckinghamshire8.4
Newlands Meadow, Edenrooftop solarrooftop solar0.1approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Buckinghamshire8.4
Big Yellow Self Storage, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024Buckinghamshire8.9
Hawes Recycling Centre, Coronation Roadrooftop solarrooftop solar0.7refusedupdated Feb 2025Nov 2024refused Feb 2025Feb 2025Buckinghamshire9.8

Distance from the average position of the HP16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar605011.5
Battery storage21001500

MW in pipeline: pending, approved and under-construction capacity.

How Buckinghamshire decides solar, wind and battery applications

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

All projects in Buckinghamshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.