Energy Projects Near You

Lye Green Energy Storage (25 MW)

Lye Green Energy Storage is a 25 MW battery storage project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 2 April 2019; the record was last updated on 27 June 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
refused on appealstatus in REPD
27 June 2019record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
21 June 2018Application submitted
9 January 2019Appeal lodged
2 April 2019Appeal refused

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
refused on appeal
Record last updated
27 June 2019
Operator or applicant
Harmony Energy Storage
Planning authority
Buckinghamshire
Planning application reference
PL/18/2421/FA
Appeal reference
APP/X0415/W/18/3212793
Address (REPD)
Land Adjacent To Electricity Transform Station Lycrome Road Chesham Buckinghamshire
Council area (by location)
Buckinghamshire
REPD reference
7195

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storagesolar farm22approved, not built3.2
Little Heath Lanesolar farm25application submitted5.5
Mop End Farm, Mop End Lanebattery storage500application submitted8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7212, -0.589).