Energy Projects Near You

Little Heath Lane (25 MW solar farm)

Little Heath Lane is a 25 MW solar farm project in Dacorum, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 11 April 2022, no decision recorded; the record was last updated on 27 April 2022. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWsolar farm
application submittedmay be out of datestatus in REPD
27 April 2022record last updated
Dacorumcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
11 April 2022Application submitted

Project details

Technology
solar farm
Capacity
25 MW
Status (REPD)
application submitted
Record last updated
27 April 2022
Operator or applicant
Energi Generation
Planning authority
Dacorum
Planning application reference
22/01106/MFA
Site area
32.0 ha
Address (REPD)
Little Heath Lane Solar Park, E/O Little Heath Lane, Berkhamsted
Council area (by location)
Dacorum
Name in REPD
Little Heath Lane - Solar PV Array
REPD reference
11085

Who decides

ApplicationsDacorumUK
Decided applications (solar, wind, battery)1710,236
Refused2 (12%)19%
Solar refused2 of 1412%
Battery storage refused0 of 316%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storagesolar farm22approved, not built4.8
Lye Green Energy Storagebattery storage25refused on appeal5.5
Beechtree Junction, Potters Crouchsolar farm49.9application submitted9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.752, -0.5273).