Energy Projects Near You

Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storage (22 MW)

Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storage is a 22 MW solar farm project in Dacorum, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 December 2025, not yet built; the record was last updated on 27 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

22 MWsolar farm
approved, not builtstatus in REPD
27 January 2026record last updated
Dacorumcouncil area

Planning timeline

DateStage
24 June 2025Application submitted
23 December 2025Planning permission granted
23 December 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
22 MW
Status (REPD)
approved, not built
Record last updated
27 January 2026
Operator or applicant
BSR Energy
Planning authority
Dacorum
Planning application reference
25/01535/MFA
Site area
56.3 ha
Address (REPD)
Pudds Cross Farm Pudds Cross Bovingdon
Council area (by location)
Dacorum
Time to decision
26 weeks
Name in REPD
Pudds Cross Farm, Pudds Cross - Solar Panels & Battery Energy Storage
REPD reference
17107

The scheme also includes 10 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsDacorumUK
Decided applications (solar, wind, battery)1710,236
Refused2 (12%)19%
Solar refused2 of 1412%
Battery storage refused0 of 316%
Median time from submission to decision11.0 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lye Green Energy Storagebattery storage25refused on appeal3.2
Little Heath Lanesolar farm25application submitted4.8
Mop End Farm, Mop End Lanebattery storage500application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7105, -0.546).