Solar, wind and battery projects near Hemel Hempstead (HP3)
29 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of HP3 (Dacorum): 5 are waiting for a planning decision, 18 approved but not yet running, 2 operational. The largest live scheme is Beechtree Junction, Potters Crouch (49.9 MW solar farm, application submitted on 4 July 2025, no decision recorded), 5.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of HP3
Projects of 1 MW and more (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Amazon Boundary Wayrooftop solar | rooftop solar | 2 | permission expiredupdated Jun 2019 | Feb 2019 | granted Jul 2019 | Jun 2019 | Dacorum | 4.2 |
| G Park Maxted Roadrooftop solar | rooftop solar | 1.2 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Jul 2022 | Jun 2022 | Dacorum | 4.2 |
| Little Heath Lanesolar farm | solar farm | 25 | application submitted may be out of dateupdated Apr 2022 | Apr 2022 | — | Apr 2022 | Dacorum | 4.2 |
| Langleybury Film Hubrooftop solar | rooftop solar | 3 | application submitted may be out of dateupdated Dec 2022 | Oct 2022 | — | Dec 2022 | Three Rivers | 5.4 |
| Beechtree Junction, Potters Crouchsolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | St Albans | 5.6 |
| Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storagesolar farm | solar farm | 22 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Dacorum | 5.8 |
| Pudds Cross Farm, Pudds Cross Solar Panels & Battery Energy Storagebattery storage | battery storage | 10 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 | Dacorum | 5.8 |
| Flamsteadbury Farmsolar farm | solar farm | 4.5 | refused on appealupdated Sep 2017 | Oct 2015 | refused Nov 2016 | Sep 2017 | St Albans | 7.3 |
| Lye Green Energy Storagebattery storage | battery storage | 25 | refused on appealupdated Jun 2019 | Jun 2018 | — | Jun 2019 | Buckinghamshire | 8.2 |
Smaller schemes under 1 MW, mostly rooftop solar (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| London Road Retail Park, Unit Arooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2026 | Jan 2026 | granted Apr 2026 | May 2026 | Dacorum | 0.4 |
| Dacorum Sports Centre, Park Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Dacorum | 1.2 |
| The Snowcentre, St Albans Hillrooftop solar | rooftop solar | 0.8 | approved, not builtupdated May 2024 | Apr 2024 | granted May 2024 | May 2024 | Dacorum | 1.3 |
| The End Of Taransey, Taransaybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | Feb 2025 | granted Jul 2025 | Jul 2025 | Dacorum | 2.4 |
| Century House, Maylands Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 | Dacorum | 3.8 |
| Iron Mountain Siterooftop solar | rooftop solar | 0.3 | operationalupdated Jan 2020 | Feb 2019 | granted Apr 2019 | Jan 2020 | Dacorum | 3.9 |
| Verge By Hemel Stags Rugby Club, Pennine Way - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 | Dacorum | 3.9 |
| G Park, Maxted Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Sep 2025 | Jun 2025 | granted Sep 2025 | Sep 2025 | Dacorum | 4.3 |
| The Mount Hmp, Molyneaux Avenuerooftop solar | rooftop solar | — | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Dacorum | 4.9 |
| Ashlyns Nursing Home, Chesham Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2025 | May 2025 | granted Sep 2025 | Oct 2025 | Dacorum | 6.7 |
| Woodside Leisure Centrerooftop solar | rooftop solar | 0.3 | operationalupdated Mar 2025 | Dec 2024 | granted Jan 2025 | Mar 2025 | Watford | 7.1 |
| Kingsway North Orbital Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2022 | Jan 2022 | granted Mar 2022 | Feb 2022 | Watford | 7.2 |
| York House School, Sarratt Roadrooftop solar | rooftop solar | 0.3 | application withdrawnupdated Jan 2026 | Sep 2025 | — | Jan 2026 | Three Rivers | 8.2 |
| The Tropical Marine Centre, Solesbridge Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Three Rivers | 8.6 |
| Westminster Lodge Leisure Centrerooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated Mar 2022 | Mar 2022 | — | Mar 2022 | St Albans | 8.6 |
| St Albans School, Abbey Gatewayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Aug 2025 | Nov 2025 | St Albans | 8.9 |
| St Albans Retail Park, Griffiths Wayrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Oct 2023 | Oct 2023 | St Albans | 9.0 |
| The Range, Graham Closerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | St Albans | 9.0 |
| The Maltings Shopping Centrerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | St Albans | 9.4 |
| Royal Masonic School, Rickmansworth Parkrooftop solar | rooftop solar | 0.1 | application submitted | Apr 2026 | — | — | Three Rivers | 9.7 |
Distance from the average position of the HP3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 4 | 2 | 1 | 0 | 1 | 96.9 |
| Rooftop solar | 21 | 3 | 14 | 2 | 0 | 9.8 |
| Battery storage | 4 | 0 | 3 | 0 | 1 | 10.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Dacorum decides solar, wind and battery applications
| Applications | Dacorum | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 17 | 10,236 |
| Refused | 2 (12%) | 19% |
| Solar refused | 2 of 14 | 12% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 11.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near HP3, 4 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.