Callie's Solar Farm is a 49.9 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 November 2022, not yet built; the record was last updated on 11 April 2022. REPD records the planning permission as expiring on 24 November 2025, but the project holds a Contracts for Difference award (AR6), so construction may have started. Check the planning authority's register for the latest position.
approved, not builtmay be out of datestatus in REPD
11 April 2022record last updated
Buckinghamshirecouncil area
application
approved
under construction
operational
REPD records the planning permission as expiring on 24 November 2025, but the project holds a Contracts for Difference award (AR6), so construction may have started.
Planning timeline
Date
Stage
15 March 2022
Application submitted
24 November 2022
Planning permission granted
24 November 2025
Permission expired
Project details
Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
11 April 2022
Operator or applicant
Low Carbon UK Solar Investment Company Limited
Planning authority
Buckinghamshire
Planning application reference
22/00986/APP
Site area
62.0 ha
Address (REPD)
Callie's Solar Farm Owlswick Road Ford
Council area (by location)
Buckinghamshire
Time to decision
36 weeks
Contracts for Difference
AR6
REPD reference
10965
Earlier applications for this site
Application
MW
Submitted
Outcome
Lower Waldridge Farm, Ford Solar Farm 21/02310/APP
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7623, -0.877).