Hale Solar Farm (40 MW)

Hale Solar Farm is a 40 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 26 March 2020, no decision recorded; the record was last updated on 17 February 2026. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
application submittedmay be out of datestatus in REPD
17 February 2026record last updated
Buckinghamshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
26 March 2020Application submitted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
application submitted
Record last updated
17 February 2026
Operator or applicant
Elgin Energy
Planning authority
Buckinghamshire
Planning application reference
20/00779/APP
Site area
69.5 ha
Address (REPD)
Hale Farm, Hulcott, Aylesbury, Buckinghamshire
Council area (by location)
Buckinghamshire
Contracts for Difference
AR7a
REPD reference
7969

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Folly Farmsolar farm13.1operational1.0
Gib Lane Solar farm (Extension)solar farm5operational1.9
Straws Hadley Solar Farmsolar farm49.9approved, not built2.3
Gib Lane (Aston Clinton solar park)solar farm24.2operational3.6
Oakwood Farmsolar farm5abandoned6.8
Ledburn, Mentmore Solar Farmsolar farm49.9approved, not built6.9
Great Seabrook Farmsolar farm5operational7.3
Moat Farm Solar Farmsolar farm24.1approved, not built7.7
Bury Farm Solar Farmsolar farm49.9approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8401, -0.7537).