Energy Projects Near You

Solar, wind and battery projects near Iver (SL0)

53 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SL0 (Buckinghamshire): 4 are waiting for a planning decision, 36 approved but not yet running, 4 operational. The largest live scheme is Pinstone Farm, Oxford Road (60 MW battery storage, application submitted on 31 July 2025, no decision recorded), 5.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

53projects within 10 km
4awaiting a decision
36approved, not running
4operational

Projects within 10 km of SL0

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Slough Roadbattery storagebattery storage57application withdrawnupdated Jan 2023Sep 2021—Jan 2023Buckinghamshire1.5
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar1.6approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Slough4.0
Sipson Roadsolarsolar6.2refusedupdated Nov 2014Jun 2014refused Oct 2014Nov 2014Hillingdon5.1
Land south of Holloway Lanesolar farmsolar farm5application withdrawnupdated Jan 2016Jul 2015—Jan 2016Hillingdon5.2
Poyle Park Solar Farmsolar farmsolar farm4.5refused on appealupdated Dec 2016Jul 2015refused Oct 2015Dec 2016Slough5.2
Galleymead House, Old Bath Roadbattery storagebattery storage2refusedupdated Apr 2024Oct 2023refused Mar 2024Apr 2024Slough5.5
Pinstone Farm, Oxford Roadbattery storagebattery storage60application submittedupdated Sep 2025Jul 2025—Sep 2025Buckinghamshire5.5
Gerrards Cross Sewage Treatment Worksbattery storagebattery storage20application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021Buckinghamshire5.9
Galvin Roadrooftop solarrooftop solar1.6abandonedupdated Feb 2017Apr 2015granted Jul 2015Feb 2017Slough7.0
Western International Marketrooftop solarrooftop solar1.7operationalupdated May 2016Jul 2015granted Sep 2015May 2016Hounslow8.2
Wraysbury Landfillsolar farmsolar farm4.8operationalupdated Jun 2017Jul 2014granted Oct 2014Jun 2017Windsor and Maidenhead8.9
Long Lane, Stanwellbattery storagebattery storage49.9approved, not builtupdated Jul 2025Dec 2024granted Jul 2025Jul 2025Spelthorne9.1
Smaller schemes under 1 MW, mostly rooftop solar (41)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Iver Water Treatment Works, Court Lanesolar farmsolar farm—approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023Buckinghamshire1.9
Langley Leisure Centre, Parlaunt Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Slough3.1
Royal Mailrooftop solarrooftop solar—approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Slough3.3
Heron Driverooftop solarrooftop solar0.3approved, not builtupdated May 2022Apr 2022granted Aug 2022May 2022Slough3.4
Hillingdon Hospital, Pield Heath Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Hillingdon3.9
Hospital Redevelopmentrooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2026Jun 2022granted Jan 2023Mar 2026Hillingdon3.9
Reliance Worldwide, buildings, 2A, 2B, 9 & 10 Horton Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted Apr 2023May 2023Hillingdon3.9
Reliance Worldwide Corporation, buildings, 3, 4, 5, 7 & 12, Horton Roadrooftop solarrooftop solar0.6approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023Hillingdon3.9
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Slough4.0
Hillingdon Sports & Leisure Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Hillingdon4.4
Slough Interchange Industrial Estate, Units 1-3, Whittenham Closerooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Slough5.2
Manor Farm, Poyle Roadbattery storagebattery storage—approved, not builtupdated Jun 2026Jan 2025granted Jun 2026Jun 2026Slough5.7
Swallowfield Wayrooftop solarrooftop solar0.4approved, not builtupdated Jun 2022May 2022granted Aug 2022Jun 2022Hillingdon6.0
Airport Gate Business Centre, Harmondsworthrooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Jun 2025granted Sep 2025Sep 2025Hillingdon6.2
Heathrow Flightpath Car Park, Bath Roadbattery storagebattery storage—approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Hillingdon6.6
Twinches Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2021Jun 2021granted Aug 2021Sep 2021Slough7.4
Oakleaf Farm, Horton Roadrooftop solarrooftop solar—approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Spelthorne7.4
Oakleaf Farm, Horton Roadrooftop solarrooftop solar—approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Spelthorne7.4
Unit 2a, Slough Retail Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Jan 2022granted Feb 2022Jan 2022Slough7.5
Lombardy Retail Park, J Sainsbury Plcrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Hillingdon7.8
Pasadena Centre, Pasadena Closerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Apr 2023Nov 2022granted Mar 2023Apr 2023Hillingdon7.8
Denham Grove Hotel, Tilehouse Lanerooftop solarrooftop solar0.3refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026Buckinghamshire8.1
Waitrose, King Edward Court Solar Panel Arrayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Windsor and Maidenhead8.1
Yeading Infant School, Carlyon Road Solar PV Systemsrooftop solarrooftop solar0.1application withdrawnupdated Sep 2024Jul 2024—Sep 2024Hillingdon8.2
Western International Market (WIM) Sitebattery storagebattery storage0.2operationalupdated May 2016Dec 2015—May 2016Hounslow8.2
International Trading Estate, Trident Way - Data Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Mar 2025granted Dec 2025Jan 2026Ealing8.4
Southall Lane Waste Depotbattery storagebattery storage—operationalupdated Nov 2022Jun 2017—Nov 2022Hounslow8.4
Lynch Hill School Primary Academy, Garrard Roadrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Slough8.4
The Windsor Boys School, Maidenhead Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Windsor and Maidenhead8.7
Tims Dairy, Denham Lanerooftop solarrooftop solar0.2application submittedMay 2026——Buckinghamshire8.7
David Lloyd Racket Club, Southall Lanerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Hounslow8.8
Micro House, Bury Street Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Hillingdon8.9
DNATA City East, Bedfont Road - Roof Mounted Solar PV Panelsrooftop solarrooftop solar0.4approved, not builtupdated Feb 2023Feb 2021granted Mar 2022Feb 2023Hounslow9.0
Dnata City, East Bedfont Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Hounslow9.0
Hatton Cross Underground Station, Southern Perimeter Road -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Hillingdon9.2
Skyline Business Park, Great South West Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Hillingdon9.4
Skyline Business Park, Great South West Roadrooftop solarrooftop solar0.4approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Hillingdon9.4
Skyline Business Park, Great South West Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Hillingdon9.4
St Johns Beaumont School, Priest Hillrooftop solarrooftop solar0.3refusedupdated Jul 2024May 2024refused Jun 2024Jul 2024Runnymede9.6
Geodis, Faggs Roadrooftop solarrooftop solar0.8approved, not builtupdated Aug 2022Jul 2022granted Aug 2022Aug 2022Hounslow9.8
London Roadbattery storagebattery storage—application submitted may be out of dateupdated Mar 2022Mar 2022—Mar 2022Spelthorne9.9

Distance from the average position of the SL0 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm401110
Rooftop solar381321210.6
Solar100010
Battery storage103321130

MW in pipeline: pending, approved and under-construction capacity.

How Buckinghamshire decides solar, wind and battery applications

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

All projects in Buckinghamshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SL0, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.