Energy Projects Near You

Solar, wind and battery projects near Uxbridge (UB10)

47 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of UB10 (Hillingdon): 5 are waiting for a planning decision, 29 approved but not yet running, 4 operational. The largest live scheme is Pinstone Farm, Oxford Road (60 MW battery storage, application submitted on 31 July 2025, no decision recorded), 6.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

47projects within 10 km
5awaiting a decision
29approved, not running
4operational

Projects within 10 km of UB10

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Slough Roadbattery storagebattery storage57application withdrawnupdated Jan 2023Sep 2021—Jan 2023Buckinghamshire4.0
Sipson Roadsolarsolar6.2refusedupdated Nov 2014Jun 2014refused Oct 2014Nov 2014Hillingdon6.2
Pinstone Farm, Oxford Roadbattery storagebattery storage60application submittedupdated Sep 2025Jul 2025—Sep 2025Buckinghamshire6.2
Gerrards Cross Sewage Treatment Worksbattery storagebattery storage20application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021Buckinghamshire6.3
Land south of Holloway Lanesolar farmsolar farm5application withdrawnupdated Jan 2016Jul 2015—Jan 2016Hillingdon6.6
Western International Marketrooftop solarrooftop solar1.7operationalupdated May 2016Jul 2015granted Sep 2015May 2016Hounslow6.7
David Lloyd Leisure, Ducks Hill Roadrooftop solarrooftop solar1refusedupdated Jul 2023Jun 2023—Jul 2023Hillingdon7.1
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar1.6approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Slough8.6
Galleymead House, Old Bath Roadbattery storagebattery storage2refusedupdated Apr 2024Oct 2023refused Mar 2024Apr 2024Slough8.9
Poyle Park Solar Farmsolar farmsolar farm4.5refused on appealupdated Dec 2016Jul 2015refused Oct 2015Dec 2016Slough9.1
Smaller schemes under 1 MW, mostly rooftop solar (37)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Hillingdon Sports & Leisure Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Hillingdon1.1
Hillingdon Hospital, Pield Heath Roadrooftop solarrooftop solar0.2approved, not builtupdated Oct 2025Aug 2025granted Sep 2025Oct 2025Hillingdon2.7
Hospital Redevelopmentrooftop solarrooftop solar—approved, not built may be out of dateupdated Mar 2026Jun 2022granted Jan 2023Mar 2026Hillingdon2.7
Reliance Worldwide, buildings, 2A, 2B, 9 & 10 Horton Roadrooftop solarrooftop solar0.6approved, not builtupdated May 2023Mar 2023granted Apr 2023May 2023Hillingdon4.4
Reliance Worldwide Corporation, buildings, 3, 4, 5, 7 & 12, Horton Roadrooftop solarrooftop solar0.6approved, not builtupdated Apr 2023Mar 2023granted Apr 2023Apr 2023Hillingdon4.4
Micro House, Bury Street Solar Arraysrooftop solarrooftop solar—approved, not builtupdated May 2025Mar 2025granted Apr 2025May 2025Hillingdon4.5
Yeading Infant School, Carlyon Road Solar PV Systemsrooftop solarrooftop solar0.1application withdrawnupdated Sep 2024Jul 2024—Sep 2024Hillingdon4.8
Swallowfield Wayrooftop solarrooftop solar0.4approved, not builtupdated Jun 2022May 2022granted Aug 2022Jun 2022Hillingdon4.9
Lombardy Retail Park, J Sainsbury Plcrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Nov 2024granted Jan 2025Jan 2025Hillingdon4.9
Iver Water Treatment Works, Court Lanesolar farmsolar farm—approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023Buckinghamshire5.1
Pasadena Centre, Pasadena Closerooftop solarrooftop solar0.4approved, not built may be out of dateupdated Apr 2023Nov 2022granted Mar 2023Apr 2023Hillingdon5.6
Sergo Park Greenford Central, Phase 1A - Industrial, Warehouse & Officesrooftop solarrooftop solar0.4approved, not builtupdated Feb 2025Jul 2024granted Jan 2025Feb 2025Ealing6.3
International Trading Estate, Trident Way - Data Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Mar 2025granted Dec 2025Jan 2026Ealing6.4
Belazu Ingredient Company, Long Driverooftop solarrooftop solar0.3approved, not builtupdated Oct 2024Aug 2024granted Oct 2024Oct 2024Ealing6.6
Western International Market (WIM) Sitebattery storagebattery storage0.2operationalupdated May 2016Dec 2015—May 2016Hounslow6.6
Southall Lane Waste Depotbattery storagebattery storage—operationalupdated Nov 2022Jun 2017—Nov 2022Hounslow6.8
Denham Grove Hotel, Tilehouse Lanerooftop solarrooftop solar0.3refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026Buckinghamshire6.8
Northwood College, Maxwell Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2023May 2023granted Jul 2023Jun 2023Hillingdon6.9
Northwood Health And Racquet Club, Ducks Hill Roadrooftop solarrooftop solar0.3application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Hillingdon7.0
David Lloyd Racket Club, Southall Lanerooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Hounslow7.2
Prologis Greenford DC1, Oldfield Lane Northrooftop solarrooftop solar0.3application submitted may be out of dateupdated Apr 2024Mar 2024—Apr 2024Ealing7.2
Mount Vernon Hospitalrooftop solarrooftop solar—operationalupdated Jan 2022Jul 2021granted Nov 2021Jan 2022Hillingdon7.3
Heathrow Flightpath Car Park, Bath Roadbattery storagebattery storage—approved, not builtupdated Jul 2025May 2025granted Jun 2025Jul 2025Hillingdon7.4
Airport Gate Business Centre, Harmondsworthrooftop solarrooftop solar0.1approved, not builtupdated Sep 2025Jun 2025granted Sep 2025Sep 2025Hillingdon7.5
David Lloyd Leisure Centrerooftop solarrooftop solar—approved, not builtupdated Nov 2025Jul 2025granted Oct 2025Nov 2025Ealing7.5
Great Western Industrial Park, Armstrong Wayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024Apr 2024granted Jun 2024Jul 2024Ealing7.8
Langley Leisure Centre, Parlaunt Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Slough7.8
Royal Mailrooftop solarrooftop solar—approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Slough8.0
Heron Driverooftop solarrooftop solar0.3approved, not builtupdated May 2022Apr 2022granted Aug 2022May 2022Slough8.1
Tims Dairy, Denham Lanerooftop solarrooftop solar0.2application submittedMay 2026——Buckinghamshire8.3
St Georges Shopping Centre, St Anns Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2025Jan 2025granted Apr 2025May 2025Harrow8.6
Headstone Lanerooftop solarrooftop solar0.6approved, not builtupdated Nov 2024Oct 2023refused Sep 2024Nov 2024Harrow8.6
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Slough8.6
Hatton Cross Underground Station, Southern Perimeter Road -Solar Panelsrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Hillingdon9.4
Manor Farm, Poyle Roadbattery storagebattery storage—approved, not builtupdated Jun 2026Jan 2025granted Jun 2026Jun 2026Slough9.4
Geodis, Faggs Roadrooftop solarrooftop solar0.8approved, not builtupdated Aug 2022Jul 2022granted Aug 2022Aug 2022Hounslow9.9
Prologis Park, Unit Brooftop solarrooftop solar1refusedupdated Jul 2024May 2024refused Jul 2024Jul 2024Hounslow9.9

Distance from the average position of the UB10 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm301010
Rooftop solar35326239
Solar100010
Battery storage8222180

MW in pipeline: pending, approved and under-construction capacity.

How Hillingdon decides solar, wind and battery applications

ApplicationsHillingdonUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused1 of 1712%
Battery storage refused0 of 116%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Hillingdon

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near UB10, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.