Sipson Road (6.2 MW solar)

Sipson Road is a 6.2 MW solar project in Hillingdon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 October 2014; the record was last updated on 23 November 2014.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar
refusedstatus in REPD
23 November 2014record last updated
Hillingdoncouncil area

Planning timeline

DateStage
2 June 2014Application submitted
30 October 2014Refused by the planning authority

Project details

Technology
solar
Capacity
6.2 MW
Status (REPD)
refused
Record last updated
23 November 2014
Operator or applicant
Costain Engineering & Construction
Planning authority
Hillingdon
Planning application reference
46223/APP/2014/1867
Address (REPD)
Adj To Sipson Road, In Holloway Lane, Harmondsworth, West Drayton, Middlesex
Council area (by location)
Hillingdon
Time to decision
21 weeks
REPD reference
2313

Who decides

ApplicationsHillingdonUK
Decided applications (solar, wind, battery)1810,236
Refused1 (6%)19%
Solar refused1 of 1712%
Battery storage refused0 of 116%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land south of Holloway Lanesolar farm5application withdrawn0.5
Long Lane, Stanwellbattery storage49.9approved, not built4.9
Slough Roadbattery storage57application withdrawn5.7
Battery Energy Storage Systembattery storage200approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.4943, -0.4642).