Energy Projects Near You

Solar, wind and battery projects near Slough (SL2)

34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SL2 (Slough): 6 are waiting for a planning decision, 19 approved but not yet running, 1 operational. The largest live scheme is Pinstone Farm, Oxford Road (60 MW battery storage, application submitted on 31 July 2025, no decision recorded), 6.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34projects within 10 km
6awaiting a decision
19approved, not running
1operational

Projects within 10 km of SL2

Projects of 1 MW and more (10)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar1.6approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Slough2.2
Galvin Roadrooftop solarrooftop solar1.6abandonedupdated Feb 2017Apr 2015granted Jul 2015Feb 2017Slough2.3
Pinstone Farm, Oxford Roadbattery storagebattery storage60application submittedupdated Sep 2025Jul 2025—Sep 2025Buckinghamshire6.6
Slough Roadbattery storagebattery storage57application withdrawnupdated Jan 2023Sep 2021—Jan 2023Buckinghamshire6.8
Gerrards Cross Sewage Treatment Worksbattery storagebattery storage20application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021Buckinghamshire7.0
Salters Lanesolar farmsolar farm42application submittedupdated Aug 2025Jul 2025—Aug 2025Buckinghamshire7.1
Car Park Legoland Windsor Resort, Winkfield Road PV solar photovoltaicrooftop solarrooftop solar1.2approved, not builtupdated Jun 2024May 2024granted Jun 2024Jun 2024Windsor and Maidenhead8.6
Poyle Park Solar Farmsolar farmsolar farm4.5refused on appealupdated Dec 2016Jul 2015refused Oct 2015Dec 2016Slough8.7
Galleymead House, Old Bath Roadbattery storagebattery storage2refusedupdated Apr 2024Oct 2023refused Mar 2024Apr 2024Slough9.3
Coldmoorholme Lane Battery Storagebattery storagebattery storage7.2refusedupdated Dec 2021Dec 2020refused Sep 2021Dec 2021Buckinghamshire9.8
Smaller schemes under 1 MW, mostly rooftop solar (24)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Lynch Hill School Primary Academy, Garrard Roadrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024Slough2.2
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Slough2.2
Twinches Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2021Jun 2021granted Aug 2021Sep 2021Slough2.7
Unit 2a, Slough Retail Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Jan 2022granted Feb 2022Jan 2022Slough2.8
Slough Interchange Industrial Estate, Units 1-3, Whittenham Closerooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023Slough2.9
Fairhouse, Burnham Roadsolar farmsolar farm0.2refusedupdated Dec 2025Sep 2025refused Nov 2025Dec 2025Buckinghamshire5.9
Waitrose, King Edward Court Solar Panel Arrayrooftop solarrooftop solar0.4approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Windsor and Maidenhead6.0
The Windsor Boys School, Maidenhead Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Windsor and Maidenhead6.0
Beaconsfield Services, Windsor Roadrooftop solarrooftop solar0.4approved, not builtupdated Apr 2026Jan 2026granted Mar 2026Apr 2026Buckinghamshire6.0
Heron Driverooftop solarrooftop solar0.3approved, not builtupdated May 2022Apr 2022granted Aug 2022May 2022Slough6.4
Langley Leisure Centre, Parlaunt Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Slough6.4
Royal Mailrooftop solarrooftop solar—approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023Slough6.6
Salters Lanesolar farmsolar farm—application submittedupdated Aug 2025Jul 2025—Aug 2025Buckinghamshire7.1
Salters Lanebattery storagebattery storage—application submittedupdated Aug 2025Jul 2025—Aug 2025Buckinghamshire7.1
John Guest Speedfit Limited, Oldfield Roadrooftop solarrooftop solar—refusedupdated Jun 2023Apr 2023refused Jun 2023Jun 2023Windsor and Maidenhead7.4
Iver Water Treatment Works, Court Lanesolar farmsolar farm—approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023Buckinghamshire7.8
Thomas Road, Wooburn Industrial Estaterooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023Buckinghamshire7.9
Iomart, Clivemont Roadrooftop solarrooftop solar0.3operationalupdated Aug 2024Jun 2023granted Aug 2023Aug 2024Windsor and Maidenhead8.3
David Lloyd Leisure Grouprooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023Buckinghamshire8.6
Tims Dairy, Denham Lanerooftop solarrooftop solar0.2application submittedMay 2026——Buckinghamshire8.9
Manor Farm, Poyle Roadbattery storagebattery storage—approved, not builtupdated Jun 2026Jan 2025granted Jun 2026Jun 2026Slough9.1
Furze Platt Senior School, Furze Platt Roadrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jun 2023Mar 2023granted May 2023Jun 2023Windsor and Maidenhead9.2
Denham Grove Hotel, Tilehouse Lanerooftop solarrooftop solar0.3refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026Buckinghamshire9.5
Hillingdon Sports & Leisure Centrerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Oct 2023granted Jan 2024Jan 2024Hillingdon9.7

Distance from the average position of the SL2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5210242
Rooftop solar22117126.8
Battery storage7310280

MW in pipeline: pending, approved and under-construction capacity.

How Slough decides solar, wind and battery applications

ApplicationsSloughUK
Decided applications (solar, wind, battery)1310,236
Refused2 (15%)19%
Solar refused1 of 1112%
Battery storage refused1 of 216%
Median time from submission to decision9.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Slough

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SL2, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.