Solar, wind and battery projects near Slough (SL1)
33 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of SL1 (Slough): 5 are waiting for a planning decision, 19 approved but not yet running, 2 operational. The largest live scheme is Pinstone Farm, Oxford Road (60 MW battery storage, application submitted on 31 July 2025, no decision recorded), 8.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of SL1
Projects of 1 MW and more (10)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Galvin Roadrooftop solar | rooftop solar | 1.6 | abandonedupdated Feb 2017 | Apr 2015 | granted Jul 2015 | Feb 2017 | Slough | 0.4 |
| Wexham Park Hospital, Wexham Streetrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 | Slough | 3.7 |
| Car Park Legoland Windsor Resort, Winkfield Road PV solar photovoltaicrooftop solar | rooftop solar | 1.2 | approved, not builtupdated Jun 2024 | May 2024 | granted Jun 2024 | Jun 2024 | Windsor and Maidenhead | 6.3 |
| Slough Roadbattery storage | battery storage | 57 | application withdrawnupdated Jan 2023 | Sep 2021 | — | Jan 2023 | Buckinghamshire | 8.3 |
| Poyle Park Solar Farmsolar farm | solar farm | 4.5 | refused on appealupdated Dec 2016 | Jul 2015 | refused Oct 2015 | Dec 2016 | Slough | 8.4 |
| Salters Lanesolar farm | solar farm | 42 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Buckinghamshire | 8.5 |
| Pinstone Farm, Oxford Roadbattery storage | battery storage | 60 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Buckinghamshire | 8.8 |
| Galleymead House, Old Bath Roadbattery storage | battery storage | 2 | refusedupdated Apr 2024 | Oct 2023 | refused Mar 2024 | Apr 2024 | Slough | 9.0 |
| Gerrards Cross Sewage Treatment Worksbattery storage | battery storage | 20 | application submitted may be out of dateupdated Jan 2021 | Dec 2020 | — | Jan 2021 | Buckinghamshire | 9.2 |
| Wraysbury Landfillsolar farm | solar farm | 4.8 | operationalupdated Jun 2017 | Jul 2014 | granted Oct 2014 | Jun 2017 | Windsor and Maidenhead | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Twinches Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2021 | Jun 2021 | granted Aug 2021 | Sep 2021 | Slough | 0.5 |
| Unit 2a, Slough Retail Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2022 | Jan 2022 | granted Feb 2022 | Jan 2022 | Slough | 0.5 |
| Lynch Hill School Primary Academy, Garrard Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Aug 2024 | Sep 2024 | Slough | 2.1 |
| Slough Interchange Industrial Estate, Units 1-3, Whittenham Closerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Slough | 2.4 |
| Wexham Park Hospital, Wexham Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Slough | 3.7 |
| The Windsor Boys School, Maidenhead Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | Windsor and Maidenhead | 3.9 |
| Waitrose, King Edward Court Solar Panel Arrayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Windsor and Maidenhead | 4.0 |
| John Guest Speedfit Limited, Oldfield Roadrooftop solar | rooftop solar | — | refusedupdated Jun 2023 | Apr 2023 | refused Jun 2023 | Jun 2023 | Windsor and Maidenhead | 6.2 |
| Heron Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2022 | Apr 2022 | granted Aug 2022 | May 2022 | Slough | 6.4 |
| Langley Leisure Centre, Parlaunt Roadrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Slough | 6.5 |
| Royal Mailrooftop solar | rooftop solar | — | approved, not builtupdated Nov 2023 | Aug 2023 | granted Nov 2023 | Nov 2023 | Slough | 6.6 |
| Iomart, Clivemont Roadrooftop solar | rooftop solar | 0.3 | operationalupdated Aug 2024 | Jun 2023 | granted Aug 2023 | Aug 2024 | Windsor and Maidenhead | 7.2 |
| Fairhouse, Burnham Roadsolar farm | solar farm | 0.2 | refusedupdated Dec 2025 | Sep 2025 | refused Nov 2025 | Dec 2025 | Buckinghamshire | 7.5 |
| Beaconsfield Services, Windsor Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Mar 2026 | Apr 2026 | Buckinghamshire | 7.8 |
| Russells Farm, Windsor Great Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Windsor and Maidenhead | 8.3 |
| Furze Platt Senior School, Furze Platt Roadrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | Windsor and Maidenhead | 8.3 |
| Salters Lanesolar farm | solar farm | — | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Buckinghamshire | 8.5 |
| Salters Lanebattery storage | battery storage | — | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 | Buckinghamshire | 8.5 |
| Iver Water Treatment Works, Court Lanesolar farm | solar farm | — | approved, not built may be out of dateupdated Jun 2023 | May 2023 | granted Jul 2023 | Jun 2023 | Buckinghamshire | 8.6 |
| St Johns Beaumont School, Priest Hillrooftop solar | rooftop solar | 0.3 | refusedupdated Jul 2024 | May 2024 | refused Jun 2024 | Jul 2024 | Runnymede | 8.6 |
| Thomas Road, Wooburn Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2023 | Oct 2023 | granted Nov 2023 | Nov 2023 | Buckinghamshire | 8.7 |
| Manor Farm, Poyle Roadbattery storage | battery storage | — | approved, not builtupdated Jun 2026 | Jan 2025 | granted Jun 2026 | Jun 2026 | Slough | 8.7 |
| David Lloyd Leisure Grouprooftop solar | rooftop solar | — | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Buckinghamshire | 9.7 |
Distance from the average position of the SL1 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 2 | 1 | 1 | 2 | 42 |
| Rooftop solar | 21 | 0 | 17 | 1 | 2 | 6.6 |
| Battery storage | 6 | 3 | 1 | 0 | 1 | 80 |
MW in pipeline: pending, approved and under-construction capacity.
How Slough decides solar, wind and battery applications
| Applications | Slough | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 13 | 10,236 |
| Refused | 2 (15%) | 19% |
| Solar refused | 1 of 11 | 12% |
| Battery storage refused | 1 of 2 | 16% |
| Median time from submission to decision | 9.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near SL1, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.