Energy Projects Near You

Renewable energy projects in Slough

13 solar, wind or battery projects of 150 kW or more are located in Slough (REPD, July 2026 extract): 0 pending, 10 approved but not running, 0 operational and 2 refused. The council refused 2 of 13 decided applications (15%; UK 19%), with a median 9 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects in the council area
0awaiting a decision
10approved, not running
15%of decisions refused

How Slough decides

ApplicationsSloughUK
Decided applications (solar, wind, battery)1310,236
Refused2 (15%)19%
Solar refused1 of 1112%
Battery storage refused1 of 216%
Median time from submission to decision9.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in Slough

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Poyle Park Solar Farmsolar farmsolar farm4.5refused on appealupdated Dec 2016Jul 2015refused Oct 2015Dec 2016
Galleymead House, Old Bath Roadbattery storagebattery storage2refusedupdated Apr 2024Oct 2023refused Mar 2024Apr 2024
Galvin Roadrooftop solarrooftop solar1.6abandonedupdated Feb 2017Apr 2015granted Jul 2015Feb 2017
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar1.6approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Slough Interchange Industrial Estate, Units 1-3, Whittenham Closerooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023
Twinches Lanerooftop solarrooftop solar0.3approved, not builtupdated Sep 2021Jun 2021granted Aug 2021Sep 2021
Heron Driverooftop solarrooftop solar0.3approved, not builtupdated May 2022Apr 2022granted Aug 2022May 2022
Lynch Hill School Primary Academy, Garrard Roadrooftop solarrooftop solar0.3approved, not builtupdated Sep 2024Jul 2024granted Aug 2024Sep 2024
Wexham Park Hospital, Wexham Streetrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026
Unit 2a, Slough Retail Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2022Jan 2022granted Feb 2022Jan 2022
Royal Mailrooftop solarrooftop solar—approved, not builtupdated Nov 2023Aug 2023granted Nov 2023Nov 2023
Manor Farm, Poyle Roadbattery storagebattery storage—approved, not builtupdated Jun 2026Jan 2025granted Jun 2026Jun 2026
Langley Leisure Centre, Parlaunt Roadrooftop solarrooftop solar—approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025

Postcode districts in Slough

DistrictProjects within 10 kmPendingApprovedOperational
SL1335192
SL2346191
SL3483353

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Slough by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.