Energy Projects Near You

Snakes Meadow Solar Farm (45.5 MW)

Snakes Meadow Solar Farm is a 45.5 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 May 2024, not yet built; the record was last updated on 30 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

45.5 MWsolar farm
approved, not builtstatus in REPD
30 June 2026record last updated
Bedfordcouncil area

Planning timeline

DateStage
12 October 2021Application submitted
8 May 2024Planning permission granted
8 May 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
45.5 MW
Status (REPD)
approved, not built
Record last updated
30 June 2026
Operator or applicant
Renewable Connections Developments Limited / European Energy UK Ltd
Planning authority
Bedford
Planning application reference
21/02526/MAF
Site area
79.6 ha
Address (REPD)
Snakes Meadow, West End, Stagsden, West End, Stagsden, Bedford
Council area (by location)
Bedford
Time to decision
134 weeks
Name in REPD
Snakes Meadow - Solar Farm
REPD reference
9820

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
The Brickmakers Arms Batterybattery storage20approved, not built5.9
Stone Lane Quarry, Woburn Road Solar Array Areasolar farm5.1application submitted6.5
Brogborough Landfill, Lidlington Solar PV parksolar farm40approved, not built6.8
Milton Keynes Wind Farmwind farm14operational6.8
Brogborough Landfill Sitewind farm5.4refused7.2
Green Lane, Stewartbysolar farm30application submitted7.2
Rectory Farm/Embertonsolar farm9operational7.3
Elstow Landfill Sitesolar farm5.5under construction8.6
Clapham Plateau Solar Farmsolar farm5.5approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1139, -0.5919).