Energy Projects Near You

The Brickmakers Arms Battery (20 MW)

The Brickmakers Arms Battery is a 20 MW battery storage project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 22 December 2021, not yet built; the record was last updated on 5 January 2022. REPD also records that the planning permission expired on 22 December 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
approved, not builtmay be out of datestatus in REPD
5 January 2022record last updated
Bedfordcouncil area

REPD also records that the planning permission expired on 22 December 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
2 February 2021Application submitted
22 December 2021Planning permission granted
22 December 2024Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
5 January 2022
Operator or applicant
FPC Industry & Enterprise 2 Limited
Planning authority
Bedford
Planning application reference
21/00300/FUL
Address (REPD)
The Brickmakers Arms Ph Woburn Road, Kempston Hardwick Bedford
Council area (by location)
Bedford
Time to decision
46 weeks
REPD reference
9668

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Green Lane, Stewartbysolar farm30application submitted2.9
Elstow Landfill Sitesolar farm5.5under construction4.8
Stone Lane Quarry, Woburn Road Solar Array Areasolar farm5.1application submitted4.8
Snakes Meadow Solar Farmsolar farm45.5approved, not built5.9
Brogborough Landfill, Lidlington Solar PV parksolar farm40approved, not built7.2
Brogborough Landfill Sitewind farm5.4refused7.3
Clapham Plateau Solar Farmsolar farm5.5approved, not built7.9
Clapham solar farmsolar farm7.5operational9.1
Thurleigh Roadbattery storage69approved, not built9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0966, -0.5107).