Energy Projects Near You

Clapham Plateau Solar Farm (5.5 MW)

Clapham Plateau Solar Farm is a 5.5 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 25 January 2023, not yet built; the record was last updated on 20 July 2022. REPD also records that the planning permission expired on 25 January 2026, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
20 July 2022record last updated
Bedfordcouncil area

REPD also records that the planning permission expired on 25 January 2026, so the project may not go ahead in this form.

Planning timeline

DateStage
8 July 2022Application submitted
25 January 2023Planning permission granted
25 January 2026Permission expired

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
approved, not built
Record last updated
20 July 2022
Operator or applicant
Sirius Renewable Energy
Planning authority
Bedford
Planning application reference
22/01581/MAF
Site area
15.3 ha
Address (REPD)
North Of College Farm Green Lane Clapham
Council area (by location)
Bedford
Time to decision
29 weeks
Name in REPD
Clapham Plateau - Solar Farm
REPD reference
11699

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clapham solar farmsolar farm7.5operational1.2
Thurleigh Roadbattery storage69approved, not built1.9
Twinwood Road Oakley And Clapham, Thurleigh Road Solar Farmsolar farm49.9approved, not built2.2
Elstow Landfill Sitesolar farm5.5under construction3.9
The Brickmakers Arms Batterybattery storage20approved, not built7.9
Snakes Meadow Solar Farmsolar farm45.5approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1657, -0.4847).