Clapham solar farm (7.5 MW)

Clapham solar farm is a 7.5 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 March 2016; the record was last updated on 23 November 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWsolar farm
operationalstatus in REPD
23 November 2016record last updated
Bedfordcouncil area

Planning timeline

DateStage
18 July 2014Application submitted
24 November 2014Planning permission granted
1 December 2015Construction started
1 March 2016Operational

Project details

Technology
solar farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
23 November 2016
Operator or applicant
SBC Renewables
Planning authority
Bedford
Planning application reference
14/01789/MAF
Site area
18.2 ha
Address (REPD)
Land North Of And Including The Baulk Clapham
Council area (by location)
Bedford
Time to decision
18 weeks
REPD reference
1947

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Twinwood Road Oakley And Clapham, Thurleigh Road Solar Farmsolar farm49.9approved, not built1.0
Thurleigh Roadbattery storage69approved, not built1.2
Clapham Plateau Solar Farmsolar farm5.5approved, not built1.2
Elstow Landfill Sitesolar farm5.5under construction5.0
The Brickmakers Arms Batterybattery storage20approved, not built9.1
Odell Glebe Solar Farmsolar farm16.8operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1767, -0.4844).