Energy Projects Near You

Twinwood Road Oakley And Clapham, Thurleigh Road Solar Farm (49.9 MW)

Twinwood Road Oakley And Clapham, Thurleigh Road Solar Farm is a 49.9 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 19 February 2026, not yet built; the record was last updated on 3 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
3 March 2026record last updated
Bedfordcouncil area

Planning timeline

DateStage
4 July 2025Application submitted
19 February 2026Planning permission granted
19 February 2029Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
3 March 2026
Operator or applicant
PACE Elevate Energy Limited
Planning authority
Bedford
Planning application reference
25/01292/MAF
Site area
170.8 ha
Address (REPD)
E/O Twinwood Road Oakley And Clapham, Se/O Thurleigh Road, Milton Ernest And Thurleigh, Bedford
Council area (by location)
Bedford
Time to decision
33 weeks
Name in REPD
Twinwood Road Oakley And Clapham, Thurleigh Road - Solar Farm
REPD reference
19369

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Thurleigh Roadbattery storage69approved, not built1.0
Clapham solar farmsolar farm7.5operational1.0
Clapham Plateau Solar Farmsolar farm5.5approved, not built2.2
Elstow Landfill Sitesolar farm5.5under construction6.0
Odell Glebe Solar Farmsolar farm16.8operational8.9
Land at Wood Roadsolar farm5refused9.3
Nun Wood (Bedford)wind farm18refused on appeal9.6
Airfield Farm (Podington)wind farm8.6operational9.9
The Brickmakers Arms Batterybattery storage20approved, not built9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1847, -0.4908).