Elstow Landfill Site (5.5 MW solar farm)

Elstow Landfill Site is a 5.5 MW solar farm project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 20 December 2021; the record was last updated on 4 May 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
under constructionstatus in REPD
4 May 2022record last updated
Bedfordcouncil area

Planning timeline

DateStage
10 September 2020Application submitted
30 November 2020Planning permission granted
20 December 2021Construction started

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
under construction
Record last updated
4 May 2022
Operator or applicant
Bedford Borough Council
Planning authority
Bedford
Planning application reference
20/01987/FULWM
Site area
6.2 ha
Address (REPD)
Elstow Landfill Site, Wilstead Road, Elstow, Bedford
Council area (by location)
Bedford
Time to decision
12 weeks
REPD reference
8013

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Clapham Plateau Solar Farmsolar farm5.5approved, not built3.9
The Brickmakers Arms Batterybattery storage20approved, not built4.8
Clapham solar farmsolar farm7.5operational5.0
Thurleigh Roadbattery storage69approved, not built5.7
Twinwood Road Oakley And Clapham, Thurleigh Road Solar Farmsolar farm49.9approved, not built6.0
Green Lane, Stewartbysolar farm30application submitted7.5
Solar Farm & Battery Storage at N/O Northill Roadsolar farm49.9application submitted7.9
Snakes Meadow Solar Farmsolar farm45.5approved, not built8.6
Stone Lane Quarry, Woburn Road Solar Array Areasolar farm5.1application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1322, -0.47).