Thurleigh Road (69 MW battery storage)

Thurleigh Road is a 69 MW battery storage project in Bedford, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 30 January 2024, not yet built; the record was last updated on 8 February 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

69 MWbattery storage
approved, not builtstatus in REPD
8 February 2024record last updated
Bedfordcouncil area

Planning timeline

DateStage
14 June 2023Application submitted
30 January 2024Planning permission granted
30 January 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
69 MW
Status (REPD)
approved, not built
Record last updated
8 February 2024
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
Bedford
Planning application reference
23/01139/MAF
Address (REPD)
Thurleigh Road, Milton Ernest, Bedford
Council area (by location)
Bedford
Time to decision
33 weeks
Name in REPD
Thurleigh Road - Battery Energy Storage
REPD reference
9651

Who decides

ApplicationsBedfordUK
Decided applications (solar, wind, battery)5010,236
Refused17 (34%)19%
Solar refused3 of 3212%
Onshore wind refused4 of 445%
Battery storage refused10 of 1416%
Median time from submission to decision15.9 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Twinwood Road Oakley And Clapham, Thurleigh Road Solar Farmsolar farm49.9approved, not built1.0
Clapham solar farmsolar farm7.5operational1.2
Clapham Plateau Solar Farmsolar farm5.5approved, not built1.9
Elstow Landfill Sitesolar farm5.5under construction5.7
Odell Glebe Solar Farmsolar farm16.8operational8.7
Land at Wood Roadsolar farm5refused8.8
Nun Wood (Bedford)wind farm18refused on appeal9.0
The Brickmakers Arms Batterybattery storage20approved, not built9.2
Snakes Meadow Solar Farmsolar farm45.5approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1792, -0.5015).