Energy Projects Near You

Brogborough Landfill, Lidlington Solar PV park (40 MW)

Brogborough Landfill, Lidlington Solar PV park is a 40 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 April 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
3 March 2022Application submitted
11 August 2023Refused by the planning authority
23 April 2024Planning permission granted
23 April 2024Appeal allowed

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Infinis Solar Developments Limited
Planning authority
Central Bedfordshire
Planning application reference
CB/22/00548/MW
Appeal reference
APP/E2530/W/24/3337544
Site area
66.3 ha
Address (REPD)
Brogborough Landfill Site, Woburn Road, Lidlington
Council area (by location)
Central Bedfordshire
Time to decision
112 weeks
Contracts for Difference
AR7a
Name in REPD
Brogborough Landfill, Lidlington - Solar PV park
REPD reference
11005

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brogborough Landfill Sitewind farm5.4refused0.4
Stone Lane Quarry, Woburn Road Solar Array Areasolar farm5.1application submitted2.7
Green Lane, Stewartbysolar farm30application submitted5.4
Snakes Meadow Solar Farmsolar farm45.5approved, not built6.8
The Brickmakers Arms Batterybattery storage20approved, not built7.2
Greenfield Road, Westoningbattery storage30approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0531, -0.5884).