Homestead Farm (Alderton) (17.6 MW solar farm)

Homestead Farm (Alderton) is a 17.6 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 23 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17.6 MWsolar farm
operationalstatus in REPD
23 March 2016record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
11 September 2014Application submitted
11 December 2014Planning permission granted
1 January 2015Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
17.6 MW
Status (REPD)
operational
Record last updated
23 March 2016
Operator or applicant
CEE
Planning authority
West Northamptonshire
Planning application reference
S/2014/1680/MAF
Address (REPD)
Land at Homestead Farm located east of the A5 and south of Alderton, (Paulerspury & Grafton Regis & Alderton Parish)
Council area (by location)
West Northamptonshire
Time to decision
13 weeks
REPD reference
2261

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Yardley Road Solar Farmsolar farm40application submitted3.3
Shacks Barn Solar Farmsolar farm5operational5.6
Silver Spinney Farmbattery storage5under construction6.2
Stonepit Farmsolar farm5operational6.3
Handley Parksolar farm5operational6.7
Mount Mill Farmsolar farm12operational7.3
Sparrow Lodge Farmsolar farm20approved, not built7.4
Salcey Green Farmsolar farm5refused7.6
M1 Wind Farmwind farm7.2operational7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1026, -0.9232).