Energy Projects Near You

Handley Park (5 MW solar farm)

Handley Park is a 5 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 March 2016; the record was last updated on 30 June 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
30 June 2016record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
21 August 2014Application submitted
23 October 2014Refused by the planning authority
8 January 2015Appeal lodged
9 September 2015Planning permission granted
9 September 2015Appeal allowed
24 March 2016Operational
1 May 2016Construction started

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
30 June 2016
Operator or applicant
Haymaker Energy
Planning authority
West Northamptonshire
Planning application reference
S/2014/1522/MAF
Appeal reference
APP/Z2830/W/14/3001220
Site area
25.5 ha
Address (REPD)
Handley Park Farm, Handley Park, Towcester
Council area (by location)
West Northamptonshire
Time to decision
55 weeks
REPD reference
2231

Earlier applications for this site

ApplicationMWSubmittedOutcome
Handley Park S/2014/0492/MAF199 April 2014refused 3 July 2014

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Shacks Barn Solar Farmsolar farm5operational1.3
Litchlake Farmbattery storage10permission expired3.9
Primrose Hill Farm, Oxford Road Solar Farmsolar farm24application submitted4.8
Homestead Farm (Alderton)solar farm17.6operational6.7
Manor Farm, Whitfieldsolar farm30application submitted8.9
Yardley Road Solar Farmsolar farm40application submitted9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1079, -1.0207).