Energy Projects Near You

Ray Valley Solar Farm (19 MW)

Ray Valley Solar Farm is a 19 MW solar farm project in Cherwell, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 22 June 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

19 MWsolar farm
under constructionstatus in REPD
22 June 2023record last updated
Cherwellcouncil area

Planning timeline

DateStage
3 February 2020Application submitted
4 December 2020Planning permission granted

Project details

Technology
solar farm
Capacity
19 MW
Status (REPD)
under construction
Record last updated
22 June 2023
Operator or applicant
Low Carbon
Planning authority
Cherwell
Planning application reference
20/00285/F
Site area
47.0 ha
Address (REPD)
Os Parcel 6086 Adjacent, Ploughley Road, Railway Line, Arncott, Bicester
Council area (by location)
Cherwell
Time to decision
44 weeks
REPD reference
7497

Who decides

ApplicationsCherwellUK
Decided applications (solar, wind, battery)4410,236
Refused6 (14%)19%
Solar refused3 of 3712%
Onshore wind refused1 of 145%
Battery storage refused2 of 616%
Median time from submission to decision10.5 weeks17.0 weeks
Appeals lodged / allowed2 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brooks Farm Solar Parksolar farm8operational0.4
Home Farm (Merton solar)solar farm18.3operational1.8
New Stone Housesolar farm12.5operational4.2
Manor Farm, Noke Solar Farmsolar farm45approved, not built6.7
Rowles Farm solar parksolar farm13operational6.8
Bicester Road, Launtonbattery storage40approved, not built7.0
Wadley Hill Farmsolar farm5refused8.7
Pool Farm, Mill Lane, Stratton Solar Farmsolar farm44approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.852, -1.1272).