Energy Projects Near You

Tar Solar Farm (49.9 MW)

Tar Solar Farm is a 49.9 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 27 June 2023, not yet built; the record was last updated on 29 November 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
29 November 2021record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
15 November 2021Application submitted
27 June 2023Planning permission granted
27 June 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 November 2021
Operator or applicant
Bluefield Renewable Developments Limited
Planning authority
West Oxfordshire
Planning application reference
21/03711/FUL
Site area
84.2 ha
Address (REPD)
Tar Farm, Tar Road, Stanton, Witney
Council area (by location)
West Oxfordshire
Time to decision
84 weeks
REPD reference
9414

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tar Solar Farmbattery storage40approved, not built<0.1
Witney Bypass, Stanton Harcourt Roadbattery storage150application submitted3.1
Aurora Solar Farmsolar farm32under construction3.4
Eynsham Solar Farmsolar farm13.2operational3.9
Ducklington Solar Farmsolar farm36under construction4.5
Aston Road, Aston Solar Panels & Battery Energy Storage Systemsolar farm40application submitted5.5
Quarry Solar Farm & Battery Storage Facilitybattery storage35approved, not built5.9
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built5.9
Caswell Lane, Brize Norton Solar Farm & Battery Storagesolar farm30application submitted7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7601, -1.4394).