Energy Projects Near You

Quarry Solar Farm & Battery Storage Facility (35 MW, REPD 16659)

Quarry Solar Farm & Battery Storage Facility is a 35 MW battery storage project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 July 2025, not yet built; the record was last updated on 22 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWbattery storage
approved, not builtstatus in REPD
22 August 2025record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
26 June 2024Application submitted
28 July 2025Planning permission granted
28 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
22 August 2025
Operator or applicant
JBM Solar Projects 34 Limited
Planning authority
West Oxfordshire
Planning application reference
24/01565/FUL
Address (REPD)
University Farm, Hailey Witney
Council area (by location)
West Oxfordshire
Time to decision
57 weeks
REPD reference
16659

Earlier applications for this site

ApplicationMWSubmittedOutcome
Quarry Solar Farm & Battery Storage Facility 23/01524/FUL—2 June 2023replaced by a revised application

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built<0.1
Akeman Solar Park & Battery Storagesolar farm20refused2.6
Witney Bypass, Stanton Harcourt Roadbattery storage150application submitted4.2
Eynsham Solar Farmsolar farm13.2operational4.3
Ducklington Solar Farmsolar farm36under construction4.7
Caswell Lane, Brize Norton Solar Farm & Battery Storagesolar farm30application submitted5.1
Tar Solar Farmsolar farm49.9approved, not built5.9
Tar Solar Farmbattery storage40approved, not built5.9
Aurora Solar Farmsolar farm32under construction6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8049, -1.4866).