Energy Projects Near You

Ducklington Solar Farm (36 MW)

Ducklington Solar Farm is a 36 MW solar farm project in West Oxfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 April 2025; the record was last updated on 12 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

36 MWsolar farm
under constructionstatus in REPD
12 May 2025record last updated
West Oxfordshirecouncil area

Planning timeline

DateStage
8 April 2021Application submitted
1 March 2022Planning permission granted
1 April 2025Construction started

Project details

Technology
solar farm
Capacity
36 MW
Status (REPD)
under construction
Record last updated
12 May 2025
Operator or applicant
Novus Renewable Services / Innova Renewables
Planning authority
West Oxfordshire
Planning application reference
21/01236/FUL
Site area
17.2 ha
Address (REPD)
Ducklington Farm Course Hill Lane Ducklington Witney
Council area (by location)
West Oxfordshire
Time to decision
47 weeks
Contracts for Difference
AR6
REPD reference
9090

Who decides

ApplicationsWest OxfordshireUK
Decided applications (solar, wind, battery)3410,236
Refused11 (32%)19%
Solar refused9 of 2612%
Battery storage refused2 of 816%
Median time from submission to decision17.0 weeks17.0 weeks
Appeals lodged / allowed3 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Witney Bypass, Stanton Harcourt Roadbattery storage150application submitted1.5
Caswell Lane, Brize Norton Solar Farm & Battery Storagesolar farm30application submitted2.8
Aston Road, Aston Solar Panels & Battery Energy Storage Systemsolar farm40application submitted3.0
Tar Solar Farmbattery storage40approved, not built4.5
Tar Solar Farmsolar farm49.9approved, not built4.5
Quarry Solar Farm & Battery Storage Facilitybattery storage35approved, not built4.7
Quarry Solar Farm & Battery Storage Facilitysolar farm35approved, not built4.7
Ventura Parkbattery storage7abandoned5.9
Eynsham Solar Farmsolar farm13.2operational6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.7645, -1.5042).