Solar, wind and battery projects near Witney (OX29)
34 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of OX29 (West Oxfordshire): 6 are waiting for a planning decision, 21 approved but not yet running, 3 operational. The largest live scheme is Botley West Solar Project (840 MW solar farm, application submitted on 15 November 2024, no decision recorded), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of OX29
Projects of 1 MW and more (27)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Eynsham Solar Farmsolar farm | solar farm | 13.2 | operationalupdated Dec 2014 | Sep 2013 | granted Dec 2013 | Dec 2014 | West Oxfordshire | 0.8 |
| Aurora Solar Farmsolar farm | solar farm | 32 | under constructionupdated Mar 2023 | Sep 2019 | granted Feb 2020 | Mar 2023 | West Oxfordshire | 2.7 |
| Aurora Solar Farmbattery storage | battery storage | 18 | under constructionupdated Mar 2023 | Sep 2019 | granted Apr 2021 | Mar 2023 | West Oxfordshire | 2.7 |
| Quarry Solar Farm & Battery Storage Facilitysolar farm | solar farm | 35 | approved, not builtupdated Feb 2026 | Jun 2024 | granted Jul 2025 | Feb 2026 | West Oxfordshire | 3.6 |
| Quarry Solar Farm & Battery Storage Facilitybattery storage | battery storage | 35 | approved, not builtupdated Aug 2025 | Jun 2024 | granted Jul 2025 | Aug 2025 | West Oxfordshire | 3.6 |
| Tar Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2021 | Nov 2021 | granted Jun 2023 | Nov 2021 | West Oxfordshire | 3.7 |
| Tar Solar Farmbattery storage | battery storage | 40 | approved, not builtupdated Oct 2025 | Jan 2025 | granted Sep 2025 | Oct 2025 | West Oxfordshire | 3.7 |
| Witney Bypass, Stanton Harcourt Roadbattery storage | battery storage | 150 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | West Oxfordshire | 4.3 |
| Akeman Solar Park & Battery Storagesolar farm | solar farm | 20 | refusedupdated Sep 2025 | Mar 2025 | refused Aug 2025 | Sep 2025 | West Oxfordshire | 5.4 |
| Akeman Solar Park & Battery Storagebattery storage | battery storage | 1.5 | refusedupdated Sep 2025 | Mar 2025 | refused Aug 2025 | Sep 2025 | West Oxfordshire | 5.4 |
| Ducklington Solar Farmsolar farm | solar farm | 36 | under constructionupdated May 2025 | Apr 2021 | granted Mar 2022 | May 2025 | West Oxfordshire | 5.6 |
| Sheehan Recycled Aggregates Plantsolar farm | solar farm | 1 | approved, not built may be out of dateupdated Dec 2021 | Dec 2020 | granted Oct 2021 | Dec 2021 | West Oxfordshire | 5.9 |
| Downs Road, Curbridge Business Parkrooftop solar | rooftop solar | 1 | approved, not builtupdated Dec 2021 | Oct 2021 | granted Dec 2021 | Dec 2021 | West Oxfordshire | 6.2 |
| Botley West Solar Projectsolar farm | solar farm | 840 | application submittedupdated Dec 2024 | Nov 2024 | — | Dec 2024 | West Oxfordshire | 6.5 |
| Caswell Lane, Brize Norton Solar Farm & Battery Storagesolar farm | solar farm | 30 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | West Oxfordshire | 7.5 |
| Caswell Lane, Brize Norton Solar Farm & Battery Storagebattery storage | battery storage | 30 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | West Oxfordshire | 7.5 |
| Southill Solarsolar farm | solar farm | 4.5 | operationalupdated Nov 2016 | Apr 2015 | granted Sep 2015 | Nov 2016 | West Oxfordshire | 7.7 |
| Aston Road, Aston Solar Panels & Battery Energy Storage Systemsolar farm | solar farm | 40 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | West Oxfordshire | 8.0 |
| Aston Road, Aston Solar Panels & Battery Energy Storage Systembattery storage | battery storage | 40 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | West Oxfordshire | 8.0 |
| Blenheim Net Zero Estatesolar farm | solar farm | 5 | under constructionupdated Feb 2024 | Aug 2020 | granted Jan 2021 | Feb 2024 | West Oxfordshire | 8.1 |
| Blenheim Net Zero Estatebattery storage | battery storage | 1 | approved, not built may be out of dateupdated Feb 2022 | Aug 2020 | granted Jan 2021 | Feb 2022 | West Oxfordshire | 8.1 |
| Woodstock Road, Yarntonbattery storage | battery storage | 52 | approved, not builtupdated Jun 2025 | Oct 2024 | granted Jun 2025 | Jun 2025 | Cherwell | 9.5 |
| Minnis Farmsolar farm | solar farm | 5 | permission expiredupdated Oct 2019 | Jun 2019 | — | Oct 2019 | Cherwell | 9.7 |
| Cornbury Park Estatesolar farm | solar farm | 5 | application withdrawnupdated Apr 2011 | Feb 2011 | — | Apr 2011 | West Oxfordshire | 9.8 |
| Essentra Components, Langford Locksrooftop solar | rooftop solar | 1 | approved, not builtupdated Jun 2024 | Apr 2024 | granted Jun 2024 | Jun 2024 | Cherwell | 9.9 |
| The Flitsolar farm | solar farm | 10.5 | operationalupdated Oct 2016 | May 2014 | granted Aug 2014 | Oct 2016 | Cherwell | 9.9 |
| Essentra Components, Langford Lanerooftop solar | rooftop solar | 1.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Cherwell | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Windrush Leisure Centrerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2025 | Jul 2025 | granted Sep 2025 | Sep 2025 | West Oxfordshire | 3.2 |
| Witney Community Hospital, Welch Way- Solar Panelsrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | West Oxfordshire | 3.7 |
| Ducklington Mill, Standlake Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | West Oxfordshire | 4.3 |
| Eynsham Fire Station, Old Station Way - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Feb 2025 | granted May 2025 | May 2025 | West Oxfordshire | 4.5 |
| Airsea Packaging, Range Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Apr 2023 | granted May 2023 | May 2023 | West Oxfordshire | 5.8 |
| Solid State Logic, Spring Hill Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Cherwell | 8.6 |
| Langford Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Cherwell | 9.9 |
Distance from the average position of the OX29 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 15 | 3 | 6 | 3 | 1 | 1,069 |
| Rooftop solar | 9 | 0 | 9 | 0 | 0 | 4.8 |
| Battery storage | 10 | 3 | 6 | 0 | 1 | 366 |
MW in pipeline: pending, approved and under-construction capacity.
How West Oxfordshire decides solar, wind and battery applications
| Applications | West Oxfordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 34 | 10,236 |
| Refused | 11 (32%) | 19% |
| Solar refused | 9 of 26 | 12% |
| Battery storage refused | 2 of 8 | 16% |
| Median time from submission to decision | 17.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 1 | — |
All projects in West Oxfordshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near OX29, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.