Energy Projects Near You

Fibden Farm, Hampton Lovett (40 MW solar farm)

Fibden Farm, Hampton Lovett is a 40 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 July 2025, not yet built; the record was last updated on 30 March 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
30 March 2026record last updated
Wychavoncouncil area

Planning timeline

DateStage
14 June 2024Application submitted
29 July 2025Planning permission granted
29 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
30 March 2026
Operator or applicant
Grenergy Renewables
Planning authority
Wychavon
Planning application reference
W/24/01088/FUL
Site area
57.5 ha
Address (REPD)
S/O Broad Alley, Hampton Lovett, Cutnall Green, Droitwich
Council area (by location)
Wychavon
Time to decision
59 weeks
Contracts for Difference
AR7a
Name in REPD
Fibden Farm, Hampton Lovett - Solar Array
REPD reference
16721

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fibden Farmsolar farm40application submitted0.9
Doverdale Solar Farm & Battery Storagebattery storage49.9operational3.5
Doverdale Solar Farm & Battery Storagesolar farm49.9operational3.5
Rectory Farm, Rectory Lanebattery storage30approved, not built3.8
Land at Rectory Farmsolar farm8.9application withdrawn4.2
Rectory Farmsolar farm8.9refused on appeal4.2
Foxwalks Farm, Grafton Lane Solar Farmsolar farm49.9approved, not built4.6
Norchard Farmsolar farm8.8approved, not built4.8
Crossway Green, Ombersleysolar farm18application submitted4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3043, -2.1585).