Energy Projects Near You

Fibden Farm (40 MW solar farm)

Fibden Farm is a 40 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 14 June 2024, no decision recorded; the record was last updated on 5 July 2024. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
application submittedmay be out of datestatus in REPD
5 July 2024record last updated
Wychavoncouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
14 June 2024Application submitted

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
application submitted
Record last updated
5 July 2024
Operator or applicant
Grenergy Renewables
Planning authority
Wychavon
Planning application reference
W/24/01088/FUL
Site area
57.2 ha
Address (REPD)
Fibden Farm, Droitwich
Council area (by location)
Wychavon
Name in REPD
Fibden Farm - Solar Array
REPD reference
15976

Who decides

ApplicationsWychavonUK
Decided applications (solar, wind, battery)5010,236
Refused3 (6%)19%
Solar refused2 of 3412%
Onshore wind refused1 of 245%
Battery storage refused0 of 1416%
Median time from submission to decision20.5 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fibden Farm, Hampton Lovettsolar farm40approved, not built0.9
Doverdale Solar Farm & Battery Storagebattery storage49.9operational2.7
Doverdale Solar Farm & Battery Storagesolar farm49.9operational2.7
Norchard Farmsolar farm8.8approved, not built3.9
Crossway Green, Ombersleysolar farm18application submitted4.0
Rectory Farm, Rectory Lanebattery storage30approved, not built4.7
Land at Rectory Farmsolar farm8.9application withdrawn5.1
Rectory Farmsolar farm8.9refused on appeal5.1
Foxwalks Farm, Grafton Lane Solar Farmsolar farm49.9approved, not built5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3054, -2.1717).