Rectory Farm (8.9 MW solar farm)

Rectory Farm is an 8.9 MW solar farm project in Wychavon, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 May 2016; the record was last updated on 30 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.9 MWsolar farm
refused on appealstatus in REPD
30 May 2016record last updated
Wychavoncouncil area

Planning timeline

DateStage
22 April 2015Application submitted
26 August 2015Refused by the planning authority
3 November 2015Appeal lodged
23 May 2016Appeal refused

Project details

Technology
solar farm
Capacity
8.9 MW
Status (REPD)
refused on appeal
Record last updated
30 May 2016
Operator or applicant
Green Switch Developments
Planning authority
Bromsgrove
Planning application reference
15/01035
Appeal reference
APP/H1840/W/15/3136031
Site area
19.2 ha
Address (REPD)
Land at Rectory Farm, Upton Warren
Council area (by location)
Wychavon
Time to decision
18 weeks
REPD reference
5895

Who decides

Bromsgrove has 7 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Rectory Farmsolar farm8.9application withdrawn0.4
Foxwalks Farm, Grafton Lane Solar Farmsolar farm49.9approved, not built0.7
Rectory Farm, Rectory Lanebattery storage30approved, not built0.7
Foxwalks Solar Farm - Extensionsolar farm13application submitted2.6
Fibden Farm, Hampton Lovettsolar farm40approved, not built4.2
Fibden Farmsolar farm40application submitted5.1
Doverdale Solar Farm & Battery Storagesolar farm49.9operational7.7
Doverdale Solar Farm & Battery Storagebattery storage49.9operational7.7
Norchard Farmsolar farm8.8approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3151, -2.0986).