Roundhill Sewage Works Wind Turbines (6.8 MW)
Roundhill Sewage Works Wind Turbines is a 6.8 MW wind farm project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 1 September 2011; the record was last updated on 8 October 2013.
6.8 MWwind farm
refused on appealstatus in REPD
8 October 2013record last updated
South Staffordshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 22 April 2010 | Application submitted |
| 9 June 2010 | Refused by the planning authority |
| 1 September 2011 | Appeal refused |
Project details
- Technology
- wind farm
- Capacity
- 6.8 MW
- Status (REPD)
- refused on appeal
- Record last updated
- 8 October 2013
- Operator or applicant
- Severn Trent Water
- Planning authority
- South Staffordshire
- Planning application reference
- 10/0232/LPAC
- Appeal reference
- 11/00019/REF
- Turbines
- 2
- Address (REPD)
- Roundhill Sewage Farm, Whittington Hall Lane, Kinver, Stourbridge, West Midlands
- Council area (by location)
- South Staffordshire
- Time to decision
- 7 weeks
- REPD reference
- 3589
Who decides
| Applications | South Staffordshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 43 | 10,236 |
| Refused | 7 (16%) | 19% |
| Solar refused | 1 of 17 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 4 of 23 | 16% |
| Median time from submission to decision | 22.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 3 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Merry Hill Shopping Centre | rooftop solar | 8.8 | approved, not built | 5.9 |
| Hinksford Substation, Hinksford Lane | battery storage | 50 | approved, not built | 6.2 |
| Wombourne Road, Wombourne | battery storage | 49.5 | approved, not built | 8.0 |
| Illey Lane | battery storage | 70 | approved, not built | 9.6 |
| Astley Solar Farm | solar farm | 5 | operational | 9.7 |
| Mucklow Hill | battery storage | 12 | permission expired | 9.8 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.452, -2.1835).