Merry Hill Shopping Centre (8.8 MW rooftop solar)

Merry Hill Shopping Centre is an 8.8 MW rooftop solar project in Dudley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 June 2025, not yet built; the record was last updated on 13 July 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.8 MWrooftop solar
approved, not builtstatus in REPD
13 July 2026record last updated
Dudleycouncil area

Planning timeline

DateStage
16 April 2025Application submitted
11 June 2025Planning permission granted

Project details

Technology
rooftop solar
Capacity
8.8 MW
Status (REPD)
approved, not built
Record last updated
13 July 2026
Operator or applicant
Unknown
Planning authority
Dudley
Planning application reference
P25/0416/PN14J
Address (REPD)
Merry Hill Shopping Centre, Pedmore Road, Brierley Hill
Council area (by location)
Dudley
Time to decision
8 weeks
Name in REPD
Merry Hill Shopping Centre - Solar Panels
REPD reference
18746

Who decides

ApplicationsDudleyUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused0 of 1612%
Battery storage refused3 of 416%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Edwin Richards Quarry, Portway Roadbattery storage100approved, not built4.4
Mucklow Hillbattery storage12permission expired5.7
Roundhill Sewage Works Wind Turbineswind farm6.8refused on appeal5.9
Hinksford Substation, Hinksford Lanebattery storage50approved, not built6.3
Illey Lanebattery storage70approved, not built6.6
Illeybrook Farmbattery storage99.8approved, not built7.3
Wombourne Road, Wombournebattery storage49.5approved, not built7.4
Lowlands Farmbattery storage50approved, not built7.9
Golds Hillbattery storage57operational8.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4815, -2.111).