Energy Projects Near You

Wombourne Road, Wombourne (49.5 MW battery storage)

Wombourne Road, Wombourne is a 49.5 MW battery storage project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 May 2025, not yet built; the record was last updated on 17 June 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWbattery storage
approved, not builtstatus in REPD
17 June 2025record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
20 December 2024Application submitted
29 May 2025Planning permission granted
29 May 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
49.5 MW
Status (REPD)
approved, not built
Record last updated
17 June 2025
Operator or applicant
Pathfinder Clean Energy UK Dev Limited
Planning authority
South Staffordshire
Planning application reference
24/01093/FULM
Address (REPD)
E/O Wombourne Road, Wombourne
Council area (by location)
South Staffordshire
Time to decision
23 weeks
Name in REPD
Wombourne Road, Wombourne - Battery Energy Storage System
REPD reference
15934

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hinksford Substation, Hinksford Lanebattery storage50approved, not built1.9
Canalsidebattery storage60approved, not built3.0
Penstone Lane, Lower Penn 2battery storage50approved, not built4.1
Penstone Lane, Penn 1battery storage50approved, not built4.2
Ebstree Road, Trysullbattery storage49.9approved, not built4.4
Ebstree Road, Trysull, Seisdonbattery storage99.9approved, not built4.4
Orchard Farm, Langley Roadbattery storage100refused4.5
South Staffordshire Railway Walk, Castlecroftbattery storage50approved, not built5.1
Wolverhampton West Sub Stationbattery storage50permission expired5.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5236, -2.1947).