Ebstree Road, Trysull, Seisdon (99.9 MW battery storage)

Ebstree Road, Trysull, Seisdon is a 99.9 MW battery storage project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 November 2025, not yet built; the record was last updated on 6 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

99.9 MWbattery storage
approved, not builtstatus in REPD
6 January 2026record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
29 May 2025Application submitted
21 November 2025Planning permission granted
21 November 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
99.9 MW
Status (REPD)
approved, not built
Record last updated
6 January 2026
Operator or applicant
NZED Projectco 3 limited
Planning authority
South Staffordshire
Planning application reference
25/00431/FULM
Address (REPD)
South of Ebstree Road Trysull, Seisdon
Council area (by location)
South Staffordshire
Time to decision
25 weeks
Name in REPD
Ebstree Road, Trysull, Seisdon - Battery Energy Storage
REPD reference
19116

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ebstree Road, Trysullbattery storage49.9approved, not built<0.1
Penstone Lane, Lower Penn 2battery storage50approved, not built1.1
Penstone Lane, Penn 1battery storage50approved, not built1.1
Canalsidebattery storage60approved, not built1.8
Pool Hall Farm, Lower Pennbattery storage100approved, not built1.9
South Staffordshire Railway Walk, Castlecroftbattery storage50approved, not built2.4
Orchard Farm, Langley Roadbattery storage100refused2.6
Wolverhampton West Sub Stationbattery storage50permission expired3.0
Wombourne Road, Wombournebattery storage49.5approved, not built4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5592, -2.2224).