Penstone Lane, Lower Penn 2 (50 MW battery storage)

Penstone Lane, Lower Penn 2 is a 50 MW battery storage project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 September 2022, not yet built; the record was last updated on 4 March 2022. REPD also records that the planning permission expired on 29 September 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtmay be out of datestatus in REPD
4 March 2022record last updated
South Staffordshirecouncil area

REPD also records that the planning permission expired on 29 September 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
18 February 2022Application submitted
29 September 2022Planning permission granted
29 September 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
4 March 2022
Operator or applicant
Anglo Renewables Limited
Planning authority
South Staffordshire
Planning application reference
22/00045/FUL
Address (REPD)
(Penn 2) Penstone Lane Lower Penn
Council area (by location)
South Staffordshire
Time to decision
32 weeks
Name in REPD
Penstone Lane, Lower Penn 2 - Battery Storage
REPD reference
10733

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penstone Lane, Penn 1battery storage50approved, not built<0.1
Ebstree Road, Trysullbattery storage49.9approved, not built1.1
Ebstree Road, Trysull, Seisdonbattery storage99.9approved, not built1.1
Canalsidebattery storage60approved, not built1.2
South Staffordshire Railway Walk, Castlecroftbattery storage50approved, not built1.4
Pool Hall Farm, Lower Pennbattery storage100approved, not built1.5
Orchard Farm, Langley Roadbattery storage100refused1.6
Wolverhampton West Sub Stationbattery storage50permission expired2.1
Wombourne Road, Wombournebattery storage49.5approved, not built4.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5603, -2.2064).