Energy Projects Near You

Canalside (60 MW battery storage)

Canalside is a 60 MW battery storage project in South Staffordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 July 2025, not yet built; the record was last updated on 5 August 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
approved, not builtstatus in REPD
5 August 2025record last updated
South Staffordshirecouncil area

Planning timeline

DateStage
14 November 2024Application submitted
14 July 2025Planning permission granted
14 July 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status (REPD)
approved, not built
Record last updated
5 August 2025
Operator or applicant
Greenfield Energy Developments Limited / Renewable Power Capital
Planning authority
South Staffordshire
Planning application reference
24/00951/FULM
Address (REPD)
S/O Flash Lane
Council area (by location)
South Staffordshire
Time to decision
35 weeks
Name in REPD
Canalside - Battery Storage System
REPD reference
17623

Who decides

ApplicationsSouth StaffordshireUK
Decided applications (solar, wind, battery)4310,236
Refused7 (16%)19%
Solar refused1 of 1712%
Onshore wind refused2 of 345%
Battery storage refused4 of 2316%
Median time from submission to decision22.9 weeks17.0 weeks
Appeals lodged / allowed2 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Penstone Lane, Lower Penn 2battery storage50approved, not built1.2
Penstone Lane, Penn 1battery storage50approved, not built1.2
Ebstree Road, Trysullbattery storage49.9approved, not built1.8
Ebstree Road, Trysull, Seisdonbattery storage99.9approved, not built1.8
Orchard Farm, Langley Roadbattery storage100refused1.9
South Staffordshire Railway Walk, Castlecroftbattery storage50approved, not built2.2
Pool Hall Farm, Lower Pennbattery storage100approved, not built2.7
Wolverhampton West Sub Stationbattery storage50permission expired2.8
Wombourne Road, Wombournebattery storage49.5approved, not built3.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5503, -2.2005).