Lowlands Farm (50 MW battery storage)

Lowlands Farm is a 50 MW battery storage project in Dudley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 September 2024, not yet built; the record was last updated on 12 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
12 September 2024record last updated
Dudleycouncil area

Planning timeline

DateStage
30 November 2022Application submitted
27 September 2023Refused by the planning authority
25 March 2024Appeal lodged
4 September 2024Appeal allowed
4 September 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
12 September 2024
Operator or applicant
Anglo Renewables
Planning authority
Dudley
Planning application reference
P22/1733
Appeal reference
APP/C4615/W/24/3341383
Address (REPD)
adj to M5 Motorway, Lowlands Farm, Illey Lane, Halesowen
Council area (by location)
Dudley
Time to decision
43 weeks
Name in REPD
Lowlands Farm - Battery Storage
REPD reference
12959

Earlier applications for this site

ApplicationMWSubmittedOutcome
Lowlands Farm P22/05415017 May 2022refused 15 August 2022

Who decides

ApplicationsDudleyUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused0 of 1612%
Battery storage refused3 of 416%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Illeybrook Farmbattery storage99.8approved, not built0.7
Illey Lanebattery storage70approved, not built1.4
Mucklow Hillbattery storage12permission expired2.6
Edwin Richards Quarry, Portway Roadbattery storage100approved, not built6.5
Fordhouse Lanebattery storage20approved, not built7.6
Merry Hill Shopping Centrerooftop solar8.8approved, not built7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4326, -2.0265).