Energy Projects Near You

Solar, wind and battery projects near Halesowen (B62)

65 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of B62 (Dudley): 3 are waiting for a planning decision, 56 approved but not yet running, 2 operational. The largest live scheme is Edwin Richards Quarry, Portway Road (100 MW battery storage, approved on 12 February 2025, not yet built), 3.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

65projects within 10 km
3awaiting a decision
56approved, not running
2operational

Projects within 10 km of B62

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mucklow Hillbattery storagebattery storage12permission expiredupdated Jan 2022Oct 2017granted Dec 2017Jan 2022Dudley0.4
Illey Lanebattery storagebattery storage70approved, not builtupdated Nov 2025Sep 2024granted Oct 2025Nov 2025Bromsgrove2.1
Illeybrook Farmbattery storagebattery storage99.8approved, not builtupdated Feb 2025Jul 2023granted Feb 2025Feb 2025Dudley2.4
Lowlands Farmbattery storagebattery storage50approved, not builtupdated Sep 2024Nov 2022refused Sep 2023Sep 2024Dudley2.7
Edwin Richards Quarry, Portway Roadbattery storagebattery storage100approved, not builtupdated Feb 2025Nov 2024granted Feb 2025Feb 2025Sandwell3.8
Broadwell Roadrooftop solarrooftop solar1approved, not builtupdated Jun 2022May 2022granted Oct 2022Jun 2022Sandwell5.7
DPD Distribution Centrerooftop solarrooftop solar1operationalupdated Feb 2017Nov 2015granted Dec 2015Feb 2017Sandwell5.8
Merry Hill Shopping Centrerooftop solarrooftop solar8.8approved, not builtupdated Jul 2026Apr 2025granted Jun 2025Jul 2026Dudley5.9
Merry Hill Centrerooftop solarrooftop solar1approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Dudley5.9
Fordhouse Lanebattery storagebattery storage20approved, not builtupdated Oct 2024Jan 2023granted Aug 2023Oct 2024Birmingham8.8
Golds Hillbattery storagebattery storage57operationalupdated Oct 2025May 2021granted Aug 2021Oct 2025Sandwell9.5
Midland Quarry Products, Smith Roadbattery storagebattery storage10approved, not builtupdated Feb 2025May 2024granted Jan 2025Feb 2025Sandwell10.0
Smaller schemes under 1 MW, mostly rooftop solar (53)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Steelpark Road, Unit G1rooftop solarrooftop solar—approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Dudley1.1
Halesowen College, Whittingham Roadrooftop solarrooftop solar—approved, not builtupdated Jun 2026May 2025granted Jun 2025Jun 2026Dudley1.2
Halesowen Leisure Centre, Great Cornbowrooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Feb 2023granted Apr 2023Aug 2023Dudley1.4
Newfield Park Primary School, Whittingham Roadrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Jul 2024granted Sep 2024Mar 2025Dudley1.5
M J Sections Limited, Stourbridge Roadrooftop solarrooftop solar—approved, not builtupdated Dec 2025Oct 2025granted Nov 2025Dec 2025Dudley1.7
Windsor High School And Sixth Formrooftop solarrooftop solar—approved, not builtupdated Jan 2022Feb 2021granted Apr 2021Jan 2022Dudley1.8
Lewis Road, Perry Hill Lane Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Sandwell2.2
Bell Heath Way, Woodgaterooftop solarrooftop solar0.6approved, not builtupdated Mar 2023Jan 2023granted Feb 2023Mar 2023Birmingham2.3
NDC Polipak, Garratts Lanerooftop solarrooftop solar0.7approved, not builtupdated Jan 2023Nov 2022granted Jan 2023Jan 2023Sandwell3.0
Rowley Regis Community Hospital, Moor Lanerooftop solarrooftop solar0.3approved, not builtupdated Aug 2025May 2025granted Jul 2025Aug 2025Sandwell3.1
York Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Sandwell3.4
Wolverhampton Road - Micro Energy Storage Facilitybattery storagebattery storage—approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Sandwell4.3
Tat Bank Road, Western Road - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sandwell4.8
Shenley Court Secondary School, Shenley Lanerooftop solarrooftop solar0.2approved, not builtupdated Aug 2023Jul 2023granted Aug 2023Aug 2023Birmingham4.9
Devonshire Infant & Junior Academies, Auckland Roadrooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jun 2025granted Jul 2025Aug 2025Sandwell5.5
Northfield, Merritts Brook Lanebattery storagebattery storage0.2approved, not builtupdated Sep 2023May 2023granted Aug 2023Sep 2023Birmingham5.6
First Steps Nursery, Waterloo Roadrooftop solarrooftop solar0.3approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Sandwell5.6
Voestalpine Metsec, Broadwell Roadrooftop solarrooftop solar0.7approved, not builtupdated May 2024Apr 2024granted May 2024May 2024Sandwell5.7
Thorns Collegiate Academyrooftop solarrooftop solar0.5approved, not builtupdated Mar 2024Jan 2024granted Mar 2024Mar 2024Dudley5.8
Navigation Drive, Hurst Business Parkrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jun 2024Jul 2024Dudley5.8
Ormiston Sandwell Community Academy, Lower City Roadrooftop solarrooftop solar0.3approved, not builtupdated Mar 2026Nov 2025granted Jan 2026Mar 2026Sandwell6.0
Bellfield Junior School, Vineyard Roadrooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Birmingham6.1
Guru Nanak Gurdwara, High Streetrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024Sandwell6.1
Unit 1, Woodside Industrial Estaterooftop solarrooftop solar0.2approved, not builtupdated Feb 2024Dec 2023granted Feb 2024Feb 2024Dudley6.3
Emr Oldbury, Union Roadrooftop solarrooftop solar1approved, not builtupdated Jan 2025Apr 2024granted Jun 2024Jan 2025Sandwell6.6
Oldbury Roadrooftop solarrooftop solar0.7approved, not builtupdated Dec 2022Nov 2022granted Dec 2022Dec 2022Sandwell6.8
Lansing Linde Creighton Limited, Dartmouth Roadrooftop solarrooftop solar0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026Sandwell6.9
Hollywood Bowl, Parkwayrooftop solarrooftop solar0.2approved, not builtupdated Oct 2024Aug 2024granted Sep 2024Oct 2024Birmingham6.9
Oxford Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Sep 2025Jul 2025refused Sep 2025Sep 2025Sandwell6.9
Morrisons Supermarket, Rubery Solar Photovoltaicsrooftop solarrooftop solar0.6approved, not builtupdated Nov 2021Nov 2021granted Jan 2022Nov 2021Birmingham7.0
Ash And Lacy, Alma Street - Photovoltaic Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Sep 2024granted Oct 2024Nov 2024Sandwell7.1
Tenpin Dudley, Castlegate Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023Dudley7.1
Bull Lane - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated May 2026Apr 2026—May 2026Sandwell7.2
David Lloyd Leisure, Pensnett Roadrooftop solarrooftop solar—approved, not builtupdated Nov 2025Sep 2025granted Nov 2025Nov 2025Dudley7.2
Dudley College, The Broadwayrooftop solarrooftop solar0.2approved, not builtupdated Jul 2026Nov 2025granted Dec 2025Jul 2026Dudley7.2
Coneygre Family Centre, Sedgley Road East - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Apr 2026Feb 2026—Apr 2026Sandwell7.3
Greets Green Playing Field, Wattle Roadbattery storagebattery storage0.2approved, not builtupdated Jun 2025Feb 2025granted May 2025Jun 2025Sandwell7.5
West Bromwich Albion Football Clubrooftop solarrooftop solar0.7approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sandwell7.5
Holyhead Road - Roof Mounted Solar PV solar panelsrooftop solarrooftop solar0.2approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024Birmingham7.8
Holyhead Roadrooftop solarrooftop solar0.4application submittedMay 2026——Birmingham7.8
Selly Park Girls School, Selly Park Roadrooftop solarrooftop solar0.3approved, not builtupdated Jun 2026Mar 2026granted Apr 2026Jun 2026Birmingham8.0
BPL Engineering, Catesby Parkrooftop solarrooftop solar0.2approved, not builtupdated Jan 2023Oct 2022granted Jan 2023Jan 2023Birmingham8.1
Tansun Limited, Spectrum Houserooftop solarrooftop solar0.2approved, not builtupdated Nov 2022Oct 2022granted Nov 2022Nov 2022Sandwell8.3
West Heath Hospital, Rednal Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026Birmingham8.5
Spartan Industrial Centre, Brickhouse Lanerooftop solarrooftop solar0.4approved, not builtupdated Mar 2025Jan 2025granted Feb 2025Mar 2025Sandwell8.5
Sedgley Road West - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Feb 2026Dec 2025granted Jan 2026Feb 2026Sandwell8.7
Cambrian Wharf, Brindley Drive - Student Accommodationrooftop solarrooftop solar0.2approved, not builtupdated May 2026Nov 2023granted Jan 2026May 2026Birmingham8.8
Ridgacre Enterprise Park, Ridgacre Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Feb 2025granted Apr 2025May 2025Sandwell8.8
Huf Uk, New Roadrooftop solarrooftop solar0.4application submitted may be out of dateupdated Feb 2024Jan 2024—Feb 2024Sandwell9.1
Upper Church Lane Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Sep 2025Jul 2025granted Sep 2025Sep 2025Sandwell9.1
Danks Waybattery storagebattery storage—approved, not built may be out of dateupdated Dec 2022Aug 2022granted Dec 2022Dec 2022Sandwell9.2
Cliff Driverooftop solarrooftop solar0.6approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Sandwell9.6
New Summer Street, Hockleybattery storagebattery storage—approved, not builtupdated Dec 2023Oct 2023granted Feb 2024Dec 2023Birmingham9.7

Distance from the average position of the B62 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar432401022.8
Battery storage2211612351

MW in pipeline: pending, approved and under-construction capacity.

How Dudley decides solar, wind and battery applications

ApplicationsDudleyUK
Decided applications (solar, wind, battery)2010,236
Refused3 (15%)19%
Solar refused0 of 1612%
Battery storage refused3 of 416%
Median time from submission to decision7.7 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Dudley

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near B62, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.