Energy Projects Near You

Astley Solar Farm (5 MW)

Astley Solar Farm is a 5 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 March 2016; the record was last updated on 2 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
2 May 2017record last updated
Shropshirecouncil area

Planning timeline

DateStage
14 May 2015Application submitted
30 September 2015Planning permission granted
9 December 2015Construction started
15 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
2 May 2017
Operator or applicant
Rockfire Capital
Planning authority
Shropshire
Planning application reference
15/02095/FUL
Address (REPD)
Astley Farm, Six Ashes, Alveley, Bridgnorth
Council area (by location)
Shropshire
Time to decision
20 weeks
REPD reference
5266

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Swancote Farm -Solar Panelssolar farm5approved, not built9.3
Roundhill Sewage Works Wind Turbineswind farm6.8refused on appeal9.7
Hinksford Substation, Hinksford Lanebattery storage50approved, not built9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4672, -2.3239).