Solar, wind and battery projects near Shifnal (TF11)
38 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TF11 (Shropshire): 3 are waiting for a planning decision, 21 approved but not yet running, 8 operational. The largest live scheme is New Works Lane Solar Farm (30 MW solar farm, application submitted on 23 July 2021, no decision recorded; REPD status may be out of date), 10.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TF11
Projects of 1 MW and more (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Kemberton Solar Farmsolar farm | solar farm | 22 | approved, not builtupdated Mar 2024 | Jun 2022 | granted Feb 2024 | Mar 2024 | Shropshire | 4.4 |
| Ricoh UK Productssolar farm | solar farm | 1.2 | operationalupdated Mar 2020 | Mar 2020 | granted Aug 2020 | Mar 2020 | Telford and Wrekin | 4.5 |
| Sheriffhales Solar Farmsolar farm | solar farm | 8.2 | operationalupdated Aug 2016 | Mar 2015 | granted Jul 2015 | Aug 2016 | Shropshire | 4.7 |
| Granville Road Solar Farmsolar farm | solar farm | 5 | operationalupdated Feb 2017 | Sep 2015 | granted Dec 2015 | Feb 2017 | Telford and Wrekin | 6.1 |
| Telford Shopping Centre Solar Photovoltaic PV Arraysolar farm | solar farm | 1.8 | approved, not built may be out of dateupdated Feb 2022 | Nov 2021 | granted Jan 2022 | Feb 2022 | Telford and Wrekin | 6.1 |
| Lyreco - Telford Distribution Centrerooftop solar | rooftop solar | 3.8 | operationalupdated Jan 2016 | — | — | Jan 2016 | Telford and Wrekin | 6.3 |
| Lyreco, Donnington Woodrooftop solar | rooftop solar | 3.8 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Dec 2025 | Mar 2026 | Telford and Wrekin | 6.3 |
| Albrighton Solar farmsolar farm | solar farm | 15.8 | operationalupdated May 2017 | Jul 2015 | granted Dec 2015 | May 2017 | Shropshire | 7.8 |
| Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm | solar farm | 23 | operationalupdated Jun 2025 | Jul 2022 | granted Jun 2023 | Jun 2025 | Shropshire | 7.9 |
| Country Lane Solar Developmentsolar farm | solar farm | 4.7 | application withdrawnupdated Jul 2017 | Oct 2015 | — | Jul 2017 | Shropshire | 8.2 |
| Albrighton Substation, Beamish Lanebattery storage | battery storage | 7 | approved, not builtupdated Mar 2024 | Nov 2023 | granted Feb 2024 | Mar 2024 | Shropshire | 8.3 |
| County Lane Solar farmsolar farm | solar farm | 16 | approved, not built may be out of dateupdated Feb 2026 | Apr 2022 | granted Mar 2023 | Feb 2026 | Shropshire | 8.3 |
| King's Streetwind farm | wind farm | 12 | refusedupdated Aug 2011 | Dec 2010 | refused Apr 2011 | Aug 2011 | South Staffordshire | 9.4 |
| New Works Lane Solar Farmsolar farm | solar farm | 30 | application submitted may be out of dateupdated Aug 2021 | Jul 2021 | — | Aug 2021 | Telford and Wrekin | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| TCL Packaging, Stafford Parkrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Apr 2025 | Jul 2025 | Telford and Wrekin | 4.1 |
| Stafford Parkbattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Nov 2024 | granted Sep 2025 | Sep 2025 | Telford and Wrekin | 4.5 |
| Halesfield 1 Roundabout, Halesfield - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | refusedupdated Sep 2025 | Jun 2025 | refused Aug 2025 | Sep 2025 | Telford and Wrekin | 4.8 |
| Mail Solutionsrooftop solar | rooftop solar | 0.6 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Telford and Wrekin | 4.9 |
| Radford House Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Nov 2024 | granted Sep 2025 | Sep 2025 | Telford and Wrekin | 4.9 |
| Ercall House, Stafford Park - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Sep 2025 | Jun 2025 | granted Aug 2025 | Sep 2025 | Telford and Wrekin | 5.3 |
| Wz Packaging, Halesfieldrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Jul 2022 | Jul 2022 | Telford and Wrekin | 5.6 |
| Euston Way Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Feb 2025 | Nov 2024 | — | Feb 2025 | Telford and Wrekin | 5.7 |
| Telford Ten Pin, International Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Oct 2023 | Nov 2023 | Telford and Wrekin | 6.0 |
| Telford Shopping Centre, Northfield Streetrooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 | Telford and Wrekin | 6.1 |
| Telford Shopping Centre, Woodhouse Centralrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Oct 2023 | Aug 2023 | granted Sep 2023 | Oct 2023 | Telford and Wrekin | 6.1 |
| Parkside Court Solar Panels & Air Source Heat Pumpsrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Jul 2022 | Jun 2022 | granted Aug 2022 | Jul 2022 | Telford and Wrekin | 6.8 |
| Duce Drive, Dawley Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Feb 2025 | Nov 2024 | — | Feb 2025 | Telford and Wrekin | 6.9 |
| Oakengates Leisure Centre, New Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Feb 2025 | Nov 2024 | — | Feb 2025 | Telford and Wrekin | 7.5 |
| Albrighton Solar farmbattery storage | battery storage | — | operationalupdated Feb 2019 | Dec 2015 | granted Dec 2015 | Feb 2019 | Shropshire | 7.8 |
| Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonbattery storage | battery storage | — | operationalupdated Jun 2025 | Jul 2022 | granted Jun 2023 | Jun 2025 | Shropshire | 7.9 |
| County Lane Solar farmbattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2026 | Apr 2022 | granted Mar 2023 | Feb 2026 | Shropshire | 8.3 |
| Makita Manufacturing Europerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Jul 2022 | Jun 2022 | Telford and Wrekin | 9.0 |
| Makita Manufacturing Europerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Telford and Wrekin | 9.0 |
| Kraft Heinz, Hortonwoodrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Jun 2026 | Mar 2026 | granted Apr 2026 | Jun 2026 | Telford and Wrekin | 9.2 |
| Cherwell Enterprise Park, Hortonwood 2 -Solar Panelsrooftop solar | rooftop solar | 0.2 | application submitted | May 2026 | — | — | Telford and Wrekin | 9.2 |
| Hortonwood Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2025 | Nov 2024 | granted Jul 2025 | Jul 2025 | Telford and Wrekin | 9.3 |
| Syspal, Cockshutt Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Dec 2022 | granted Jan 2023 | Jan 2023 | Shropshire | 9.6 |
| Buildwas Bankbattery storage | battery storage | — | approved, not builtupdated Sep 2025 | Sep 2023 | granted Aug 2025 | Sep 2025 | Telford and Wrekin | 9.6 |
Distance from the average position of the TF11 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 1 | 3 | 5 | 0 | 69.8 |
| Rooftop solar | 14 | 2 | 11 | 1 | 0 | 8.9 |
| Wind farm | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 13 | 0 | 7 | 2 | 1 | 7.8 |
MW in pipeline: pending, approved and under-construction capacity.
How Shropshire decides solar, wind and battery applications
| Applications | Shropshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 98 | 10,236 |
| Refused | 22 (22%) | 19% |
| Solar refused | 20 of 78 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 0 of 17 | 16% |
| Median time from submission to decision | 15.2 weeks | 17.0 weeks |
| Appeals lodged / allowed | 10 / 5 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TF11, 6 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.