Albrighton Solar farm (15.8 MW)

Albrighton Solar farm is a 15.8 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 February 2017; the record was last updated on 31 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.8 MWsolar farm
operationalstatus in REPD
31 May 2017record last updated
Shropshirecouncil area

Planning timeline

DateStage
24 July 2015Application submitted
14 December 2015Planning permission granted
28 November 2016Construction started
28 February 2017Operational

Project details

Technology
solar farm
Capacity
15.8 MW
Status (REPD)
operational
Record last updated
31 May 2017
Operator or applicant
Big 60 Million
Planning authority
Shropshire
Planning application reference
15/02787/FUL
Site area
29.7 ha
Address (REPD)
Land To The North of Harriotts Hayes Lane, Codsall Wood, Wolverhampton
Council area (by location)
Shropshire
Time to decision
20 weeks
REPD reference
5506

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Albrighton Substation, Beamish Lanebattery storage7approved, not built0.5
County Lane Solar farmsolar farm16approved, not built0.7
Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm23operational2.8
Chillington Estate, Chillington Parksolar farm40approved, not built3.8
Land East of Lawn Lanesolar farm5operational7.3
Jaguar Land Roverrooftop solar5.8operational7.5
Lawn Lane, Coven Solar Farmsolar farm48approved, not built7.5
Pool Hall Farm, Lower Pennbattery storage100approved, not built7.9
Wolverhampton West Sub Stationbattery storage50permission expired8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6395, -2.2507).