Energy Projects Near You

County Lane Solar farm (16 MW)

County Lane Solar farm is a 16 MW solar farm project in Shropshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 March 2023, not yet built; the record was last updated on 16 February 2026. REPD records the planning permission as expiring on 21 March 2026, but the project holds a Contracts for Difference award (AR7a), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
approved, not builtmay be out of datestatus in REPD
16 February 2026record last updated
Shropshirecouncil area

REPD records the planning permission as expiring on 21 March 2026, but the project holds a Contracts for Difference award (AR7a), so construction may have started.

Planning timeline

DateStage
14 April 2022Application submitted
21 March 2023Planning permission granted
21 March 2026Permission expired

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Boultbee Brooks Renewable Energy Limited
Planning authority
Shropshire
Planning application reference
22/01816/FUL
Site area
30.4 ha
Address (REPD)
The W/O County Lane, Albrighton, Wolverhampton
Council area (by location)
Shropshire
Time to decision
49 weeks
Contracts for Difference
AR7a
Name in REPD
County Lane - Solar farm
REPD reference
9119

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsShropshireUK
Decided applications (solar, wind, battery)9810,236
Refused22 (22%)19%
Solar refused20 of 7812%
Onshore wind refused2 of 345%
Battery storage refused0 of 1716%
Median time from submission to decision15.2 weeks17.0 weeks
Appeals lodged / allowed10 / 5—

Other large projects within 10 km

ProjectTypeMWStatuskm
Albrighton Substation, Beamish Lanebattery storage7approved, not built0.3
Albrighton Solar farmsolar farm15.8operational0.7
Solar Farm & Battery Storage at The South Of Holyhead Road Albrightonsolar farm23operational2.6
Chillington Estate, Chillington Parksolar farm40approved, not built3.9
Land East of Lawn Lanesolar farm5operational7.0
Jaguar Land Roverrooftop solar5.8operational7.1
Pool Hall Farm, Lower Pennbattery storage100approved, not built7.2
Lawn Lane, Coven Solar Farmsolar farm48approved, not built7.2
Wolverhampton West Sub Stationbattery storage50permission expired8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.6347, -2.2451).